60 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
A. Work breakdown structure
B. milestone review and schedule technique
C. cost/schedule control system
D. planning programming budget system
E. program and evaluation review technique
第1题:
146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A. Time, schedule and cost.
B. Management coordination and organization structuring.
C. Work methods and accountability.
D. Quality of work.
E. Risk and impact decision-making
第2题:
120 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第3题:
38 The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A. Selecting the wrong person as the project manager
B. Selecting the wrong person as the sponsor
C. Accepting a high-risk project
D. Ill-defined requirements
E. All of the above
第4题:
96 A negative cost variance and positive schedule variance means:
A. The project is under budget and ahead of schedule
B. The project is over budget and behind schedule
C. The project is over budget and ahead of schedule
D. The project will be overrun but ahead of schedule at completion
第5题:
● Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
第6题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第7题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第8题:
In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)
A.the quality of the schedule and cost control analysis
B.customer satisfaction
C.customer compromise in defining its needs
D.exceeding customer requirements through gold-plating
第9题:
第10题:
第11题:
第12题:
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
第13题:
99 Scope management is:
A. a project control function.
B. employs change control.
C. a work authorization process.
D. considers Cost, Quality and Schedule.
E. All of the above
第14题:
178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
A. Work breakdown structure
B. milestone review and schedule technique
C. cost/schedule control system
D. planning programming budget system
E. program and evaluation review technique
第15题:
57 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above.
第16题:
139 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above
第17题:
● The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project
D Ill-defined requirements
E All of the above
第18题:
● Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
第19题:
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.
(71)
A. Quantitative Risk Analysis
B. Qualitative Risk Analysis
C. Enterprise Environmental Factors
D. Risk Management Plan
第20题:
A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list
A.Essences
B.Elements
C.Purposes
D. Issues
第21题:
第22题:
第23题:
The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.