更多“177 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A. 5%B. 10%C. 15%D. 25%E. 50%”相关问题
  • 第1题:

    It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A . Direct labor dollars

    B . Direct labor hours.

    C . Overhead rates.

    D . Procurement costs.

    E . None of the above.


    正确答案:B

  • 第2题:

    Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

    A concept

    B development

    C execution

    D conclusion

    E All of the above.


    正确答案:A

  • 第3题:

    67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual

    B. Development.

    C. Execution

    D. Finish

    E. All of the above


    正确答案:E

  • 第4题:

    95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A. 5%

    B. 10%

    C. 15%

    D. 25%

    E. 50%


    正确答案:D

  • 第5题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第6题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第7题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第8题:

    ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

    A Conceptual

    B Development.

    C Execution

    D Finish

    E All of the above.


    正确答案:E

  • 第9题:

    The (71) defines the phases that connect the beginning of a project to its end.

    A.milestone

    B.schedule

    C.temporary

    D.project life cycle


    正确答案:D

  • 第10题:

    A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
    The life cycle provides the basic for managing the project, regardless of the specific work involved.

    A.phases
    B.processes
    C.segments
    D. pieces

    答案:A
    解析:
    一个项目的生命周期由若干个顺序相连的(73)组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的。
    (73)A. 阶段 B. 过程 C. 片段 D. 碎片

  • 第11题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第12题:

    The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:

  • 第13题:

    During which phase of the project life cycle is the amount at stake lowest?

    A concept

    B development

    C execution

    D conclusion

    E C and D


    正确答案:A

  • 第14题:

    19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A. Direct labor dollars

    B. Direct labor hours.

    C. Overhead rates.

    D. Procurement costs.

    E. None of the above


    正确答案:B

  • 第15题:

    70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

    B. development

    C. execution

    D. conclusion

    E. All of the above


    正确答案:A

  • 第16题:

    194 During which phase of the project life cycle is the amount at stake lowest?

    A. concept

    B. development

    C. execution

    D. conclusion

    E. C and D


    正确答案:A

  • 第17题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第18题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第19题:

    ● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A 5%

    B 10%

    C 15%

    D 25%

    E 50%


    正确答案:D

  • 第20题:

    A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.

    A.phases

    B.processes

    C.segments

    D.pieces


    正确答案:A

  • 第21题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().

    A.development

    B.concept

    C.system analysis

    D.implementation


    正确答案:B

  • 第22题:

    A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.

    A. plan
    B. fraction
    C. main
    D.framework

    答案:D
    解析:
    一个项目的生命周期由若干个顺序相连的阶段组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的()

  • 第23题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施