73 The following individuals are responsible for determining the content of the Communications Management Plan.A. Project SponsorB. Task Manager(s)C. Director of CommunicationsD. Project Manager

题目

73 The following individuals are responsible for determining the content of the Communications Management Plan.

A. Project Sponsor

B. Task Manager(s)

C. Director of Communications

D. Project Manager


相似考题
更多“73 The following individuals are responsible for determining the content of the Communications Management Plan.A. Project SponsorB. Task Manager(s)C. Director of CommunicationsD. Project Manager”相关问题
  • 第1题:

    Which of the following fall(s) under the responsibilities of a project manager?

    A . Labor relations with project personnel

    B . Affirmative action

    C . Personnel training

    D . Discrimination and equal employment opportunity

    E . All of the above


    正确答案:E

  • 第2题:

    The way a project manager sends and receives information depends upon:

    A How others relate to the project manager

    B The project manager's level in the organizational hierarchy

    C the size and nature of the project

    D the project manager's salary and age

    E the number of projects going on at one time in the company


    正确答案:A

  • 第3题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第4题:

    69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

    A. budget, schedule

    B. quality requirements, schedule

    C. size, type of industry

    D. nature, size

    E. project manager, sponsor


    正确答案:D

  • 第5题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第6题:

    ● Which of the following planning considerations is often overlooked?

    A Planning for project termination.

    B Qualified project manager assignment.

    C Insuring top management support.

    D Clearly defined tasks.

    E All of the above.


    正确答案:A

  • 第7题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第8题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第9题:

    Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).

    A.change the scope baseline

    B.contact the customer to determine if the change adds value

    C.call a meeting of the change control board

    D.change the project’s objectives


    正确答案:C
    项目经理相信调整范围能为客户增加收益,项目经理应该(73)。A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。

  • 第10题:

    In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law,a project with 10 stakeholders has ( ) potential communication channels.

    A.10
    B.45
    C.50
    D.100

    答案:B
    解析:
    在沟通过程的需求分析中,项目经理应该考虑项目沟通的复杂性,将潜在的沟通渠道或路径的数量作为一个指标来计算。根据麦特卡夫定律,一个项目有10个项目干系人的时候,将有(73)条潜在的沟通渠道。

  • 第11题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D

  • 第12题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    projectcharter


    正确答案: D
    解析: 该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。

  • 第13题:

    The following individuals are responsible for determining the content of the Communications Management Plan.

    A Project Sponsor

    B Task Manager(s)

    C Director of Communications

    D Project Manager


    正确答案:D

  • 第14题:

    108 The way a project manager sends and receives information depends upon:

    A. How others relate to the project manager

    B. The project manager's level in the organizational hierarchy

    C. the size and nature of the project

    D. the project manager's salary and age

    E. the number of projects going on at one time in the company


    正确答案:A

  • 第15题:

    161 Which of the following planning considerations is often overlooked?

    A. Planning for project termination.

    B. Qualified project manager assignment.

    C. Insuring top management support.

    D. Clearly defined tasks.

    E. All of the above.


    正确答案:A

  • 第16题:

    155 The following individuals are responsible for determining the content of the Communications Management Plan.

    A. Project Sponsor

    B. Task Manager(s)

    C. Director of Communications

    D. Project Manager


    正确答案:D

  • 第17题:

    ● Scope Management:

    A entails managing the project's work content.

    B is a subset of configuration management and as such is performed by CM specialists.

    C is concerned with naming all activities performed, the end products which results and the resources consumed.

    D is not a concern of the project manager.

    E None of the above.


    正确答案:C

  • 第18题:

    ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

    (73) A. change the scope baseline

    B. contact the customer to determine if the change adds value

    C. call a meeting of the change control board

    D. change the project' s objectives


    正确答案:B

  • 第19题:

    ● In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project' s communications. According to Metcalfe's Law, a project with 10 stakeholders has ( 73 ) potential communication channels.

    (73) A. 10

    B. 45

    C. 50

    D. 100


    正确答案:B

  • 第20题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第21题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第22题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第23题:

    The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

    • A、Data flow model
    • B、The project critical path
    • C、Resource loading chart
    • D、WBS (Work Breakdown Structure)

    正确答案:B