更多“36 A Work Breakdown Structure:A. assures all work is identifiedB. subdivides the project into manageable segmentsC. provides the project sponsor with a time-phase task summaryD. both A and BE. All of the above”相关问题
  • 第1题:

    What tool have project managers come to use to identify all of the costs associated with a project.

    A . A bill of materials

    B . A Gantt chart

    C . An arrow diagram network.

    D . A work breakdown structure.

    E . B and C only.


    正确答案:D

  • 第2题:

    The primary source document for establishing the content of the Project Status Report is:

    A The project charter

    B The Project Plan

    C The ASTM Project Document Guide

    D The summary work breakdown structure


    正确答案:B

  • 第3题:

    29 The WBS is:

    A. An organization oriented family tree of the project.

    B. A task oriented family tree of the project.

    C. A cost centered structure of the project.

    D. Only required on large complex projects where separately identifiable work packages are difficult to construct.

    E. None of the above


    正确答案:B

  • 第4题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第5题:

    198 What tool have project managers come to use to identify all of the costs associated with a project. A. A bill of materials

    B. A Gantt chart

    C. An arrow diagram network.

    D. A work breakdown structure.

    E. B and C only


    正确答案:D

  • 第6题:

    80 What tool have project managers come to use to identify all of the costs associated with a project.

    A. A bill of materials

    B. A Gantt chart

    C. An arrow diagram network.

    D. A work breakdown structure.

    E. B and C only


    正确答案:D

  • 第7题:

    94 The primary source document for establishing the content of the Project Status Report is:

    A. The project charter

    B. The Project Plan

    C. The ASTM Project Document Guide

    D. The summary work breakdown structure


    正确答案:B

  • 第8题:

    ● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A The project manager

    B The functional manager

    C The project sponsor

    D The client

    E All of the above


    正确答案:A

  • 第9题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第10题:

    A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第11题:

    In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.

    A.RBS
    B.PBS
    C.GBS
    D.WBS

    答案:D
    解析:
    在项目管理和系统工程中,WBS是将项目分解为更小的组件的可交付成果。这是一个重要的项目交付成果,将团队的工作组织到可管理的部分。

  • 第12题:

    The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

    • A、Data flow model
    • B、The project critical path
    • C、Resource loading chart
    • D、WBS (Work Breakdown Structure)

    正确答案:B

  • 第13题:

    Which of the following would most likely increase the accuracy of estimating the project cost?

    A . Pricing out the work at lower levels in the work breakdown structure.

    B . Using historical data.

    C . Talking to people who have worked on similar projects.

    D . All of the above.

    E . A and C only.


    正确答案:D

  • 第14题:

    87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.

    B. Using historical data.

    C. Talking to people who have worked on similar projects.

    D. All of the above.

    E. A and C only.


    正确答案:D

  • 第15题:

    35 The project charter:

    A. Expresses upper management commitment to the project.

    B. Provides that authority by which the project will be run.

    C. Establishes that organizational structure with the project.

    D. Specifies overall objectives and timeframe. of the project.

    E. All of the above


    正确答案:E

  • 第16题:

    154 A Work Breakdown Structure:

    A. assures all work is identified

    B. subdivides the project into manageable segments

    C. provides the project sponsor with a time-phase task summary

    D. both A and B

    E. All of the above


    正确答案:D

  • 第17题:

    142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A. The project manager

    B. The functional manager

    C. The project sponsor

    D. The client

    E. All of the above


    正确答案:A

  • 第18题:

    86 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above


    正确答案:D

  • 第19题:

    168 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above.


    正确答案:D

  • 第20题:

    ● A Work Breakdown Structure:

    A assures all work is identified

    B subdivides the project into manageable segments

    C provides the project sponsor with a time-phase task summary

    D both A and B

    E All of the above.


    正确答案:D

  • 第21题:

    ● The project charter:

    A Expresses upper management commitment to the project.

    B Provides that authority by which the project will be run.

    C Establishes that organizational structure with the project.

    D Specifies overall objectives and timeframe. of the project.

    E All of the above.


    正确答案:E

  • 第22题:

    A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Functional decomposition diagram
    B.Work Breakdown Structure
    C.Structure Chart
    D.Organizational Structure

    答案:B
    解析:

  • 第23题:

    The intention of the ( ) is to schedule,organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

    A.project work breakdown
    B.project security authentication
    C.project management
    D.project flowchart

    答案:C
    解析:
    项目管理的目的就是计划,组织和控制项目的活动来达到最终的目的。A.项目工作分解 B.项目安全认证C.项目管理 D.项目流程图