64 The financial closeout of a project dictates that:A. All project funds have been spent.B. No charge numbers have been overrun.C. No follow-on work from this client is possible.D. No further charges can be made against the project.E. All of the above

题目

64 The financial closeout of a project dictates that:

A. All project funds have been spent.

B. No charge numbers have been overrun.

C. No follow-on work from this client is possible.

D. No further charges can be made against the project.

E. All of the above


相似考题
参考答案和解析
正确答案:D
更多“64 The financial closeout of a project dictates that:A. All project funds have been spent.B. No charge numbers have been overrun.C. No follow-on work from this client is possible.D. No further charges can be made against the project.E. All of the above”相关问题
  • 第1题:

    You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:

    A.The project is operating at a favorable cost efficiency ratio.

    B.the project is spending more than planned

    C.the project is behind schedule

    D.the project is ahead of schedule

    E.B and C


    正确答案:C
    C

  • 第2题:

    35 The project charter:

    A. Expresses upper management commitment to the project.

    B. Provides that authority by which the project will be run.

    C. Establishes that organizational structure with the project.

    D. Specifies overall objectives and timeframe. of the project.

    E. All of the above


    正确答案:E

  • 第3题:

    167 The project life-cycle can be described as:

    A. project concept, project planning, project execution, and project close-out.

    B. project planning, work authorization, and project reporting.

    C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

    E. All of the above


    正确答案:A

  • 第4题:

    193 Creation of project objectives:

    A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.

    B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.

    D. all of the above.

    E. A and B only


    正确答案:E

  • 第5题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第6题:

    86 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above


    正确答案:D

  • 第7题:

    168 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above.


    正确答案:D

  • 第8题:

    ● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A The project manager

    B The functional manager

    C The project sponsor

    D The client

    E All of the above


    正确答案:A

  • 第9题:

    ● The financial closeout of a project dictates that:

    A All project funds have been spent.

    B No charge numbers have been overrun.

    C No follow-on work from this client is possible.

    D No further charges can be made against the project.

    E All of the above.


    正确答案:D

  • 第10题:

    Free pratique means that ______.

    A.clearance requirements for all regulatory bodies have been met

    B.health requirements have been met and no further quarantine formalities are required

    C.shipment will be made at no cost

    D.tonnage taxes are not required to be paid


    正确答案:B

  • 第11题:

    单选题
    It is recommended that the project _____ until all the preparations have been made.
    A

    not be started

    B

    will not be started

    C

    is not started

    D

    is not to be started


    正确答案: C
    解析:
    句意:建议在所有的准备工作完成之前,这项工程不要开始。It is recommended后面的主语从句用虚拟语气,用“should+动词原形”的形式,should可省略,因此本题选择A项。

  • 第12题:

    单选题
    It is recommended that the project ______ until all the preparations have been made.
    A

    not be started  

    B

    will not be started

    C

    is not started  

    D

    is not to be started


    正确答案: C
    解析:
    建议在所有的准备工作完成之前,这项工程不要开始。It is recommended后面的主语从句用虚拟语气,用“should+动词原形”的形式,should可省略,因此本题选择A项。

  • 第13题:

    182 The financial closeout of a project dictates that:

    A. All project funds have been spent.

    B. No charge numbers have been overrun.

    C. No follow-on work from this client is possible.

    D. No further charges can be made against the project.

    E. All of the above


    正确答案:D

  • 第14题:

    154 A Work Breakdown Structure:

    A. assures all work is identified

    B. subdivides the project into manageable segments

    C. provides the project sponsor with a time-phase task summary

    D. both A and B

    E. All of the above


    正确答案:D

  • 第15题:

    171 Documented work authorization provide:

    A. a means of effective internal coordination of the project's activities.

    B. an audit trail of all work authorized from project initiation to completion

    C.a means for communication of work activity between the project manager and the performing activities.

    D. All of the above

    E. A and B only


    正确答案:D

  • 第16题:

    142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A. The project manager

    B. The functional manager

    C. The project sponsor

    D. The client

    E. All of the above


    正确答案:A

  • 第17题:

    39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:

    A. The project is operating at a favorable cost efficiency ratio.

    B. the project is spending more than planned

    C. the project is behind schedule

    D. the project is ahead of schedule

    E. B and C


    正确答案:C

  • 第18题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第19题:

    ● The scope of a project can be expected to change if:

    A The project manager must provide cost estimates without having a design concept

    B Oversimplification (underestimating) of the nature of the work occurs

    C The project manager is assigned after the project is defined, and the cost and schedule are approved

    D A clear objective is not provided

    E All of the above are possible based upon the situation


    正确答案:E

  • 第20题:

    ● A Work Breakdown Structure:

    A assures all work is identified

    B subdivides the project into manageable segments

    C provides the project sponsor with a time-phase task summary

    D both A and B

    E All of the above.


    正确答案:D

  • 第21题:

    ________ can be done ________ been done.

    A.All that...has

    B.All that...have

    C.All...has

    D.All...have


    正确答案:A
    解析:本题考查主谓一致的用法。由 all that 引导的主语从句“all that can be done”(所有能被做的事情)应视为单数,所以整个句子的谓语动词也应该用单数形式,构成现在  完成时的被动语态:has been done。句意:“所有能做的都做了。”

  • 第22题:

    All that can be done.

    A.have been done
    B.have done
    C.has been done
    D.has done

    答案:C
    解析:

  • 第23题:

    单选题
    Free pratique means that ().
    A

    clearance requirements for all regulatory bodies have been met

    B

    health requirements have been met and no further quarantine formalities are required

    C

    shipment will be made at no cost

    D

    tonnage taxes are not required to be paid


    正确答案: A
    解析: 暂无解析