● Which of the following factors has historically been the greatest contributor to project failure?
A Planning performed by a planning group.
B Poor financial estimates.
C Lack of sufficient management reserve.
D Lack of management support.
E Not using an automated tracking tool.
第1题:
Contingency planning should include all but which of the following?
A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.
B the development of schedule alternatives and work-around
C the management of a contingency budget
D an assessment of project shut-down liabilities.
E A and C
第2题:
1 Contingency planning should include all but which of the following?
A. The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.
B the development of schedule alternatives and work-around
C. the management of a contingency budget
D. an assessment of project shut-down liabilities.
E. A and C
第3题:
● Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
第4题:
Financial Planning: the factors involved in deciding on appropriate pricing strategies
第5题:
● Risk management allows the project manager and the project team not to(71).
(71)
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第6题:
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第7题:
Risk management allows the project manager and the project team not to (71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第8题:
第9题:
第10题:
The inputs of developing project management plan do not include()
第11题:
When planning for a logically partitioned system,which of the following should be used as part of a review to ensure that each partition has the required resources? ()
第12题:
project charter
stakeholder management strategy
project scope statement
outputs from planning processes
第13题:
121 Project management/project planning is most closely aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C
第14题:
161 Which of the following planning considerations is often overlooked?
A. Planning for project termination.
B. Qualified project manager assignment.
C. Insuring top management support.
D. Clearly defined tasks.
E. All of the above.
第15题:
● Which of the following planning considerations is often overlooked?
A Planning for project termination.
B Qualified project manager assignment.
C Insuring top management support.
D Clearly defined tasks.
E All of the above.
第16题:
● The inputs of developing project management plan do not include (72).
(72)
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
第17题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第18题:
According to the passage, which of the following about the borrower's financial weakness is false?
A.Past record of repayment.
B.Low profitability.
C.Poor management.
D.Heavy obligations to creditors.
第19题:
第20题:
第21题:
第22题:
Which of the following wireless service components occur in the implement phase?()
第23题:
Which of the following functions can be performed using the Integrated Virtualization Manager?()