Which of the following steps are necessary in order to add a new VLAN to the Ezonexam switched network? (Select all that apply)
A.Create the VLAN.
B.Name the VLAN.
C.Configure an IP address for the VLAN.
D.Add the desired ports to the new VLAN.
E.Add the VLAN to the VTP domain.
第1题:
A new switch is installed in the Ezonexam network. This switch is to be configured so that VLAN information will be automatically distributed to all the other Cisco Catalyst switches in the network.
Which of the conditions below have to be met in order for this to occur? (Choose all that apply).
A. The switch that will share the VLAN information must be in the VTP Server mode.
B. The switches must be in the same VTP domain.
C. The switch that will share the VLAN information must be configured as the root bridge.
D. The switches must be configured to use the same VTP version.
E. The switches must be configured to use the same STP version.
F. The switches must be configured to use the same type of ID tagging.
G. The switches must be connected over VLAN trunks.
第2题:
You need to create a new VLAN on your Catalyst switch. This VLAN is to be named EZONEXAM. Which of the following need to be completed for the creation of this new VLAN? (Select all that apply)
A. The EZONEXAM VLAN must be created.
B. The desired ports must be added to the new EZONEXAM VLAN.
C. The EZONEXAM VLAN must be added to all of the domains.
D. The EZONEXAM VLAN must be named.
E. An IP address must be configured for the EZONEXAM VLAN.
F. None of the above. VLAN creations are automatic.
第3题:
A. The TESTKING VLAN must be created.
B. The desired ports must be added to the new TESTKING VLAN.
C. The TESTKING VLAN must be added to all of the domains.
D. The TESTKING VLAN must be named.
E. An IP address must be configured for the TESTKING VLAN.
F. None of the above. VLAN creations are automatic.
第4题:
A. Create the VLAN.
B. Name the VLAN.
C. Configure an IP address for the VLAN.
D. Add the desired ports to the new VLAN.
E. Add the VLAN to the VTP domain.
第5题:
A switch is configured with all ports assigned to vlan 2 with full duplex FastEthernet to segment existing departmental traffic. What is the effect of adding switch ports to a new VLAN on the switch?()
A.More collision domains will be created.
B.IP address utilization will be more efficient.
C.More bandwidth will be required than was needed previously.
D.An additional broadcast domain will be created.
第6题:
You have just created a new VLAN on your network for inter-VLAN routing. What is one step that you should include in your VLAN-based implementation and verification plan?()
第7题:
Which of the following steps are necessary in order to add a new VLAN to a switched network?()
第8题:
A new VLAN needs to be created for an existing network. Which of the following are the minimum tasks that must be accomplished in order to create the new VLAN?()
第9题:
You have just created a new VLAN on your network. What is one step that you should include in your VLAN-based implementation and verification plan? ()
第10题:
STP
GVRP
SNMP
VTP
DHCP
第11题:
STP
VTP
GVRP
SNMP
DHCP
第12题:
STP
VTP
EIGRP
SNMP
CDP
None of the above
第13题:
Which one of the following protocols allows the information about the configuration of a new VLAN to be distributed across entire switched network?
A. STP
B. VTP
C. EIGRP
D. SNMP
E. CDP
F. None of the above
第14题:
You are an administrator of a switched network and your goal is to reduce some of the administrative overhead on your network. You plan on achieving this by configuring a new VLAN for each department in your network. However, you need to share the VLAN information across numerous switches throughout your network.Which of the following would allow you accomplish this?()
A.STP
B.GVRP
C.SNMP
D.VTP
E.DHCP
第15题:
A. The VLAN must be created
B. The VLAN must be named
C. An IP address and subnet mask must be configured for the new VLAN
D. The desired ports must be added to the new VLAN
E. The VLAN must be added to the existing VTP Domain
第16题:
A. STP
B. VTP
C. GVRP
D. SNMP
E. DHCP
第17题:
Which one of the following protocols allows the information about the configuration of a new VLAN to be distributed across entire switched network?()
第18题:
Which protocol reduces administrative overhead in a switched network by allowing the configuration of a new VLAN to be distributed to all the switches in a domain?()
第19题:
A switch is configured with all ports assigned to vlan 2 with full duplex FastEthernet to segment existing departmental traffic. What is the effect of adding switch ports to a new VLAN on the switch?()
第20题:
You have just created a new VLAN on your network. What is one step that you should include in your VLAN based implementation and verification plan? ()
第21题:
Which two of the following steps are necessary to configure inter-VLAN routing between multilayer switches?()
第22题:
Create the VLAN.
Name the VLAN.
Configure an IP address for the VLAN.
Add the desired ports to the new VLAN.
Add the VLAN to the VTP domain.
第23题:
The VLAN must be created
The VLAN must be named
An IP address and subnet mask must be configured for the new VLAN
The desired ports must be added to the new VLAN
The VLAN must be added to the existing VTP Domain