参考答案和解析
正确答案:B
更多“●Maintenance activities do not include (74).(74) A. making enhancements to software produc ”相关问题
  • 第1题:

    ●Software (75)occurs following delivery ofa software product to the customer.

    (75)

    A.analysis

    B.design

    C.implementation

    D.maintenance


    正确答案:D

  • 第2题:

    Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

    A.cost management plan
    B.risk management
    C.scope management plan
    D.management schedule

    答案:D
    解析:
    翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划

  • 第3题:

    The term “software( )" is used to describe the software engineering activities that occur following delivery of a software product to the customer.

    A.analysis
    B.design
    C.implementation
    D.maintenance

    答案:D
    解析:

  • 第4题:

    ● Which of the following is not part of a modern quality management concept?(74)

    (74)

    A.Performance standard is zero defects

    B.Quality must be inspected in

    C.85% of failures occur because of the process, not the worker

    D.Quality is a 4 cycle process – plan/do/check/act


    正确答案:B

  • 第5题:

    Software ( ) activities involve making enhancements to software products, adapting products to new environments, and correcting problems.

    A.analysis
    B.design
    C.coding
    D.maintenance

    答案:D
    解析:
    软件维护活动包括增强软件产品、调整软件产品以适应新的环境和纠正软件中的问题。