The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).
A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
第1题:
The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A . Multiplying the actual hours worked on the project by the budgeted labor rate.
B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C . Dividing the actual hours required to complete the task by the budgeted labor rate.
D . Cannot be determined.
E . None of the above
第2题:
Project leadership requires that the project manager pay attention simultaneously to the:
A . Tasks to be performed and needs of the team
B . Quantity and quality of the work to be performed
C . Efficiency and effectiveness of the team
D . Time, cost and performance deliverables
E . All of the above
第3题:
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A. Multiplying the actual hours worked on the project by the budgeted labor rate.
B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C. Dividing the actual hours required to complete the task by the budgeted labor rate.
D. Cannot be determined.
E. None of the above
第4题:
114 The Cost Performance Index is computed as:
A. budget cost of work performed divided by actual cost of work performed
B. budget cost of work performed minus actual cost of work performed
C. budget cost of work performed minus budget cost of work scheduled
D. budget cost of work scheduled divided by budget cost of work performed
E. actual cost of work scheduled divided by budget cost of work performed
第5题:
68 The Cost Performance Index (CPI) measures:
A. cost of work performed vs planned costs.
B. work performed vs cost of work performed.
C. work performed vs planned work.
D. direct costs vs indirect costs.
E. floating costs vs. sunk costs.
第6题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第7题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第8题:
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
(74)A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第9题:
The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.
A.cost variance
B.planned cost
C.planned cost
D.actual cost
第10题:
第11题:
第12题:
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
第13题:
The planned cost for the total project at its inception is called the _____.
A . Cost of goods sold.
B . Depreciable value.
C . Budgeted cost.
D . All of the above.
E . B and C only.
第14题:
146 The planned cost for the total project at its inception is called the _____.
A. Cost of goods sold.
B. Depreciable value.
C. Budgeted cost.
D. All of the above.
E. B and C only
第15题:
18 The difference between the BCWS and the BCWP is referred to as the:
A. Schedule variance
B Cost variance.
C. Estimate of completion
D. Actual cost of the work performed
E. None of the above
第16题:
100 The difference between the BCWS and the BCWP is referred to as the:
A. Schedule variance
B. Cost variance.
C. Estimate of completion
D. Actual cost of the work performed
E. None of the above
第17题:
135 Using the cumulative cost curve in the special window, height B represents
A. actual cost to date
B. total budgeted costs for the project
C. planned cost for month 6
D. cost variance
E. earned value
第18题:
is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
第19题:
Any difference between the fair market values of the securities and their cost is a realized gain or loss.()
第20题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第21题:
is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
第22题:
第23题: