In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)A.the quality of the schedule and cost control analysisB.customer satisfactionC.customer compromise in defining its needsD.exceeding

题目

In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)

A.the quality of the schedule and cost control analysis

B.customer satisfaction

C.customer compromise in defining its needs

D.exceeding customer requirements through gold-plating


相似考题
参考答案和解析
正确答案:B
所有项目中,客户的要求必须根据进度表、成本和有限的资源进行修改。项目的成功主要取决于:A进度表和成本控制分析的优劣B.客户满意程度C客户在确定要求时的折衷态度D通过漂亮的外包装超额满足客户的要求所以答案选B。
更多“In all projects,needs must be tempered by schedule,cost and resource constraints.Project s ”相关问题
  • 第1题:

    A Project Status Report would include all of the following except:

    A Cost and schedule reports

    B Changes to scope. cost or schedule

    C Narrative explanation of variances

    D Personnel problems on the project

    E Upcoming activities


    正确答案:D

  • 第2题:

    130 What is the relative priority of project Cost, Schedule and Quality?

    A. 1)Cost - 2)Schedule - 3)Quality

    B. 1)Quality - 2)Schedule - 3)Cost

    C. 1)Quality - 2)Cost - 3)Schedule

    D. 1)Schedule - 2)Quality - 3)Cost

    E. All are of equal priority


    正确答案:E

  • 第3题:

    127 Cost management includes processes that are required to maintain financial control of projects. These processes may include:

    A. economic evaluation

    B. cost estimating

    C. cost forecasting

    D. B and C

    E. All of the above


    正确答案:E

  • 第4题:

    57 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above.


    正确答案:C

  • 第5题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating

    B.activity resource estimating, activity duration estimating, schedule development

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating


    参考答案:B

  • 第6题:

    123 The scope of a project can be expected to change if:

    A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

    C. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not provided

    E. All of the above are possible based upon the situation


    正确答案:E

  • 第7题:

    ● Which of the following are types of status reports?

    A document, variance, trend and exception

    B cost, trend, schedule and acquisition

    C cost, schedule, technical performance

    D analysis, cost, performance and schedule

    E All of the above.


    正确答案:C

  • 第8题:

    ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development


    正确答案:D

  • 第9题:

    Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.

    A.accuracy

    B.approxination

    C.specification

    D.summary


    正确答案:B

  • 第10题:

    Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.

    A.PERT B.Resource levelling C.Schedule compression D.Critical chain method


    正确答案:B

  • 第11题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第12题:

    单选题
    Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
    A

    activity

    B

    work

    C

    currency

    D

    time


    正确答案: C
    解析: 阅读试题可知,整段文章讨论的内容集中于"Costestimating",分析问题(1)的语句结构为"estimatingscheduleactivitycosts(主语)involves(谓语)developingan(1)ofthecostoftheresources"。接下来使用排除法,如果对于"estimatingscheduleactivitycosts"的特定内容不了解,似乎哪个选项也可以,注意"thelresourcesneededtocompleteeachscheduleactivity",既然每项活动所需的资源都需考虑,那就只能选择答案summary,summary在此处解释为"汇总"。分析问题(2)对应的语句,"costestimates(主语)aregenerallyexpressed(谓语)inunitsof(2)tofacilitatecomparisonsbothwithinandacrossprojects",结合选项,此句的含义为"成本估算(结果)通常以作为单位",故而只能选择C,Currency的含义为"货币"、"通货",考生即使不熟悉这个单词,也能轻易排除其他三个选项。问题(3)对应的语句,"the(3)(主语)describes(谓语)importantinformationaboutprojectrequirementthatisconsideredduringcostestimating",所以该句的含义即"描述了成本估算时应考虑的项目需求"。显而易见,选项C和D容易排除,但选择"Projectscopestatement"还是"Scopeofwork"?Scopeofwork(工作说明书)是合同中的附件,用于说明合同的工作范围(此时项目尚未建立),因而选择选项A。

  • 第13题:

    In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

    A Work breakdown structure

    B milestone review and schedule technique

    C cost/schedule control system

    D planning programming budget system

    E program and evaluation review technique


    正确答案:A

  • 第14题:

    178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

    A. Work breakdown structure

    B. milestone review and schedule technique

    C. cost/schedule control system

    D. planning programming budget system

    E. program and evaluation review technique


    正确答案:A

  • 第15题:

    41 The scope of a project can be expected to change if:

    A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

    C. The project manager is assigned after the project is defined, and the cost and schedule are approved

    D. A clear objective is not provided

    E. All of the above are possible based upon the situation


    正确答案:E

  • 第16题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第17题:

    The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing


    参考答案:A

    该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

  • 第18题:

    139 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above


    正确答案:C

  • 第19题:

    ● The scope of a project can be expected to change if:

    A The project manager must provide cost estimates without having a design concept

    B Oversimplification (underestimating) of the nature of the work occurs

    C The project manager is assigned after the project is defined, and the cost and schedule are approved

    D A clear objective is not provided

    E All of the above are possible based upon the situation


    正确答案:E

  • 第20题:

    ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

    (71)

    A.activity duration estimating, schedule developing, activity resource estimating

    B . activity resource estimating, activity duration estimating, schedule development

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating


    正确答案:B
    试题(71)分析
     项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
     项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
     以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
    参考答案
    (71)B

  • 第21题:

    On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.project planning

    B.time estimating

    C.cost estimating

    D.schedule development


    正确答案:D

  • 第22题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A、time estimating
    • B、cost estimating
    • C、project planning
    • D、schedule development

    正确答案:C

  • 第23题:

    单选题
    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
    A

    activity duration estimating, schedule developing, activity resource estimating

    B

    activity resource estimating, activity duration estimating, schedule development

    C

    schedule developing, activity resource estimating, activity duration estimating

    D

    activity resource estimating, schedule developing, activity duration estimating


    正确答案: A
    解析: 暂无解析