●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.(75) A. Resource assignment matrixB. Change control planC. Project charterD. C

题目

●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.

(75) A. Resource assignment matrix

B. Change control plan

C. Project charter

D. Client organization chart


相似考题
更多“●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.(75) A. Resource assignment matrixB. Change control planC. Project charterD. C”相关问题
  • 第1题:

    182 The use of the project reports:

    A. are not necessary on small projects

    B. provides a means whereby various levels of authority can judge project performance

    C. provides insight into project areas and the effectiveness of the control systems

    D. All of the above

    E. B and C


    正确答案:E

  • 第2题:

    94 The primary source document for establishing the content of the Project Status Report is:

    A. The project charter

    B. The Project Plan

    C. The ASTM Project Document Guide

    D. The summary work breakdown structure


    正确答案:B

  • 第3题:

    ● The use of the project reports:

    A are not necessary on small projects

    B provides a means whereby various levels of authority can judge project performance

    C provides insight into project areas and the effectiveness of the control systems

    D All of the above

    E B and C


    正确答案:E

  • 第4题:

    ● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).

    (75)

    A.assign change tasks to project members

    B.call a meeting of the configuration control board

    C.change the scope baseline

    D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


    正确答案:B

  • 第5题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第6题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第7题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第8题:

    ( )is a process developing a document that formally authorizes the existence of a project and provides the
    project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor and Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第9题:

    ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor anD.Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第10题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第11题:

    Which factor has the greatest impact on the estimated per unit labor cost for a project?()

    • A、Historical information
    • B、Use of outside vendors
    • C、Change control processes
    • D、Human resource skill level requirements

    正确答案:D

  • 第12题:

    单选题
    You develop a Web control. The Web control consists of labels and associated text boxes. You need to ensure that the Web control has both toolbox and visual designer support. What should you do? ()
    A

    Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.

    B

    Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.

    C

    Add a Web User Control to your project. Define a class that inherits from UserControl.

    D

    Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.


    正确答案: A
    解析: 暂无解析

  • 第13题:

    42 Which of the following organizations has the best technical project control?

    A. matrix

    B. functional

    C. projectized

    D. B and C

    E. A and B


    正确答案:D

  • 第14题:

    145 The initial document that formally recognizes the existence of a project is the _____ .

    A. Scope baseline

    B. Management plan

    C. Project charter

    D. Configuration control report

    E. None of the above


    正确答案:C

  • 第15题:

    ● A comprehensive definition of scope management would be:

    A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.

    B Approval of the scope baseline.

    C Approval of the detailed project charter.

    D Configuration control.

    E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.


    正确答案:A

  • 第16题:

    ● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

    (75)

    A. Project Scope Statement

    B. Project Management Plan

    C. Forecasts

    D. Project Charter


    正确答案:B

    试题(75)分析
      项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
      A.项目范围说明书                    B.项目管理计划
      C.项目预测                          D.项目章程
    参考答案
      (75)B

  • 第17题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第18题:

    You develop a Web control. The Web control consists of labels and associated text boxes.You need to ensure that the Web control has both toolbox and visual designer support. What should you do?()

    A. Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.

    B. Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.

    C. Add a Web User Control to your project. Define a class that inherits from UserControl.

    D. Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.


    参考答案:A

  • 第19题:

    The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

    A.change control board

    B. project management office

    C.project manager

    D.configuration management officer


    正确答案:C
    本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。

  • 第20题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第21题:

    Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.

    A.Resource assignment matrix
    B.Change control plan
    C.Project charter
    D.Client organization chart

    答案:B
    解析:
    在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,变更控制计划文件提供了该信息。 A.资源分配矩阵 B.变更控制计划 C.项目章程 D.客户组织结构图

  • 第22题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D

  • 第23题:

    You develop a Web control. The Web control consists of labels and associated text boxes. You need to ensure that the Web control has both toolbox and visual designer support. What should you do?()

    • A、Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.
    • B、Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.
    • C、Add a Web User Control to your project. Define a class that inherits from UserControl.
    • D、Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl..

    正确答案:A