The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . …

题目

The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……

A.Monitoring

B.Managing

C.Gathering

D.Reducing


相似考题
更多“The project maintains a current and approved set of requirements over the life of the proj ”相关问题
  • 第1题:

    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第2题:

    174 A project may be defined as _____

    A. an integrated approach to managing projects

    B. a coordinated undertaking of interrelated activities.

    C. a group of activities directed by a project manger over a life cycle

    D. an undertaking with a defined starting point and defined objectives

    E. All of the above


    正确答案:D

  • 第3题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第4题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第5题:

    A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.

    A.phases

    B.processes

    C.segments

    D.pieces


    正确答案:A

  • 第6题:

    ● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

    (75)

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D
    试题(75)分析
     质量分析成本Cost of quality analysis是对产品或服务进行需求一致性分析所产生的成本;
     成本效益分析Cost-Benefit analysi是通过比较项目的全部成本和效益来评估项目价值的一种方法;
     控制图Control charts是项目质量控制方法;
     质量功能展开Quality function deployment是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法
     因此,因此选D
    参考答案
    (75)D

  • 第7题:

    If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan. Are revised and reissued to reflect the approved changes

    A.developing baselines

    B.testing baselines

    C.schedule baselines

    D.ending baselines


    正确答案:C

  • 第8题:

    A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.

    A. plan
    B. fraction
    C. main
    D.framework

    答案:D
    解析:
    一个项目的生命周期由若干个顺序相连的阶段组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的()

  • 第9题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施

  • 第10题:

    If the approved change requests have an effect on the project scope,then the corresponding component documents and cost baselines,and( )of the project management plan are revised and reissued to reflect the approved changes.

    A.developing baselines
    B.testing baselines
    C.schedule base lines
    D.ending baselines

    答案:C
    解析:
    如果批准的变更请求对项目范围的影响,那么相应的组件文件和成本基线,和进度基线的项目管理计划。修订再版反映批准的变更。(75) A.发展基线 B.测试基线 C.进度基线 D.结束基线

  • 第11题:

    current life table


    正确答案: 现时寿命表,指从一个横断面看问题,假定有同时出生的一代人,按照某种人群现实人口实际年龄组死亡率陆续死去,计算出这一代人按年龄的一系列指标。

  • 第12题:

    单选题
    The minimum amount of lifesaving equipment required aboard an 85-foot uninspected towing vessel consists of().
    A

    one approved flotation cushion for each person on board

    B

    one approved life preserver for each person on board and one life ring

    C

    one approved inflatable vest for each person on board

    D

    lifeboat capacity equal to 1 1/2 times the number of persons on board


    正确答案: A
    解析: 暂无解析

  • 第13题:

    121 The quality objectives are approved in the conceptual stage of the project by the:

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:E

  • 第14题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第15题:

    Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.

    A.reviewing

    B.estimating

    C.auditing

    D.expecting


    参考答案:B

    该题的关键词为"scheduling、executing、monitoring、controlling",其语句结构为‘‘Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",分析后得知空白处的选项应该和上述的关键词为并列的词语,且顺序排列在其他的关键词之前,因而只能选择选项B,因为只有首先进行项目估算,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。

  • 第16题:

    ● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:

    · (73) all changes to the requirements

    · Maintaining the relationships among the requirements, the project plansand the work products

    · ……

    (73)

    A. Monitoring

    B. Managing

    C. Gathering

    D. Reducin


    正确答案:B

  • 第17题:

    It seems that the new project in Nanjing will be even() than your current project.

    A、good

    B、best

    C、better


    参考答案:C

  • 第18题:

    Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D

  • 第19题:

    A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
    The life cycle provides the basic for managing the project, regardless of the specific work involved.

    A.phases
    B.processes
    C.segments
    D. pieces

    答案:A
    解析:
    一个项目的生命周期由若干个顺序相连的(73)组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的。
    (73)A. 阶段 B. 过程 C. 片段 D. 碎片

  • 第20题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第21题:

    ()are?those?costs?that?cannot?be?directly?traced?to?a specific?project?and?therefore?will?be?accumulated?and allocated?equitably?over?multiple?projects?by?some?approved and?documented?accounting?procedure.

    A.Direct costs
    B.Operation costs
    C.Indirect costs
    D.Implement costs

    答案:C
    解析:
    本题翻译:
    ()是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。
    A.直接成本B.运营成本C.间接成本D.实施成本
    本题考查成本的分类,不能直接的就可以理解为间接,间接成本:来自一般管理费用科目或几个项目共同负担的项目成本所分摊给本项目的费用。
    而成本管理中不是涉及运营成本、实施成本。排除BD选项。所以此题选择C选项。

  • 第22题:

    A person′s calorie requirements vary______ his life.

    A.across
    B.throughout
    C.over
    D.within

    答案:B
    解析:
    考查介词辨析。across“穿过,横穿”,throughout“贯穿,遍及”,over“在……的上方,越过”,within“在……之内,在……里面”。句意为“人一生中对卡路里的需求是不同的”。Throughoutone’s life意为“在某人一生中,终生”,符合题意,故答案为B。

  • 第23题:

    单选题
    Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
    A

    reviewing

    B

    estimating

    C

    auditing

    D

    expecting


    正确答案: C
    解析: 该题的关键词为"scheduling、executing、monitoring、controlling",其语句结构为''Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",分析后得知空白处的选项应该和上述的关键词为并列的词语,且顺序排列在其他的关键词之前,因而只能选择选项B,因为只有首先进行项目估算,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。