()is the process of documenting,analyzing,tracing,prioriiting on requirements and then controlling change and communicating to stakeholders it is a continuous process throughout a projectA.integratend managementB.configurationmanagemenC.scopemanagementD.r

题目

()is the process of documenting,analyzing,tracing,prioriiting on requirements and then controlling change and communicating to stakeholders it is a continuous process throughout a project

A.integratend management

B.configurationmanagemen

C.scopemanagement

D.requirementmanagement


相似考题
更多“()is the process of documenting,analyzing,tracing,prioriiting on requirements and then con ”相关问题
  • 第1题:

    ●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).

    (73)A. project management plan

    B. project baseline

    C. risk response plan

    D. risk baseline


    正确答案:A

  • 第2题:

    ()is the process of determining. documenting and managing stakeholder needs and requirements to meet project objectives

    A.Collecting requirements

    B.Defining requirements

    C.Creating WBS

    D.Requirements analysis


    正确答案:A

  • 第3题:

    Requirements management is the process of (1),analyzing,tracing,prioritizing andagreeing on requirements and then controlling changes and communicating to relevantstakeholders.

    A.communicating

    B.collecting

    C.filing

    D.documenting


    正确答案:D
    需求管理过程是(1),分析,跟踪,优先考虑和同意的要求并控制变化和沟通,利益相关者。A、沟通B、收集C、归档D、编制

  • 第4题:

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

    A.Activity list

    B.Work Breakdown Structures

    C.Activity Attributes

    D.Milestone Lists


    正确答案:B

  • 第5题:

    ()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.

    A.identify risks
    B.monitor risks
    C.implement risks responses
    D.plan risk management

    答案:A
    解析:
    翻译:()是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。
    A.识别风险
    B.监控风险
    C.实施风险应对措施
    D.计划风险管理
    识别风险是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。

  • 第6题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第7题:

    Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders.

    A.communicating
    B.collecting
    C.filing
    D.documenting

    答案:D
    解析:
    需求管理是针对需求进行(过程记录),分析,跟踪,优先考虑,控制变更并与相关干系人沟通的过程。
    A.沟通 B.收集 C.归档 D.编制、记录

  • 第8题:

    You are maintaining an OLTP database in Oracle10g. You set the value of the LOG_ARCHIVE_TRACE parameter to zero. What is the impact of this setting? () 

    • A、 The trace files will be disabled only for a specific session.
    • B、 Tracing will be disabled for a client identifier.
    • C、 Tracing will be disabled only for the ARCn process.
    • D、 The SQL Trace facility will be disabled for the instance.

    正确答案:C

  • 第9题:

    Requirements management is the process of ()

    • A、communicating
    • B、collecting
    • C、filing
    • D、documenting 

    正确答案:D

  • 第10题:

    单选题
    Which best describes the customer benefit of developing business requirements in the prepare phase?()
    A

    reduce unnecessary disruption, delays, rework, and other problems by establishing test cases for use in verifying that the system meets operational, functional, and interface requirements

    B

    improve its ability to make sound financial decisions by developing a business case based on its business requirements and establishing a basis for developing a technology strategy

    C

    reduce operating costs and limit change-related incidents by providing a consistent and efficient set of processes

    D

    improve the return on investment and hasten migration by identifying and planning for necessary infrastructure changes and resource additions, as well as reduce deployment costs by analyzing gaps early in the planning process to determine what is needed to support the system


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a()process throughout a project. A requirement is a capability to which a project outcome(product or service)should conform.
    A

    persistent

    B

    continuing

    C

    permanent

    D

    continuous


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    Requirements management is the process of ()
    A

    communicating

    B

    collecting

    C

    filing

    D

    documenting 


    正确答案: D
    解析: 暂无解析

  • 第13题:

    ● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

    (75)

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D
    试题(75)分析
     质量分析成本Cost of quality analysis是对产品或服务进行需求一致性分析所产生的成本;
     成本效益分析Cost-Benefit analysi是通过比较项目的全部成本和效益来评估项目价值的一种方法;
     控制图Control charts是项目质量控制方法;
     质量功能展开Quality function deployment是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法
     因此,因此选D
    参考答案
    (75)D

  • 第14题:

    Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.

    A.communicating

    B.collecting

    C.filing

    D.documenting


    正确答案:D

  • 第15题:

    Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D

  • 第16题:

    In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.

    A.Activity list
    B.Work Break down Structures
    C.Activity Attributes
    D.Mile stone Lists

    答案:B
    解析:
    翻译:在项目管理中,活动定义是识别和记录项目可交付物而采取的具体行动的过程。( )不是活动定义的输出。A.活动清单 B.工作分解结构 C.活动属性 D.里程碑清单

  • 第17题:

    Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .

    A.project management plan
    B.project baseline
    C.riskresponse plan
    D.risk baseline

    答案:A
    解析:
    风险管理和记录它们是非常重要的在项目规划过程。在过程定义关键风险中,包括约束和假设,应对计划和对突发事件的处理。这些细节将被包含在项目管理计划中。

  • 第18题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第19题:

    ( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

    • A、Integrated management
    • B、Configuration management
    • C、Scope management
    • D、Requirements management

    正确答案:D

  • 第20题:

    Which three business requirements development activities are performed in the prepare phase before creating a technology strategy? ()

    • A、 identifying and assessing customer business requirements
    • B、 documenting and categorizing customer business requirements in terms of performance, availability, capacity and security
    • C、 producing a documented technology strategy
    • D、 creating a bill of materials
    • E、 presenting documented business requirements to a customer and having the customer validate them
    • F、 completing a site survey

    正确答案:A,B,E

  • 第21题:

    单选题
    You are maintaining an OLTP database in Oracle10g. You set the value of the LOG_ARCHIVE_TRACE parameter to zero. What is the impact of this setting? ()
    A

     The trace files will be disabled only for a specific session.

    B

     Tracing will be disabled for a client identifier.

    C

     Tracing will be disabled only for the ARCn process.

    D

     The SQL Trace facility will be disabled for the instance.


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    What is a useful tool to get solution requirements and pricing in the sales process?()
    A

    Smart Assist

    B

    Quote Builder

    C

    Partner Central

    D

    Visio


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
    A

    Riskldentification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: A
    解析: 该题的关键词为"ascertains、documenting the risks' characteristics",其语句结构为"The()_process(主语)ascertains(谓语)which risks have the potential of affecting the project and documenting the risks' characteristics",含义为"什么过程确定那些可能影响项目的风险并记录这些风险特征",根据风险管理知识领域,识别并记录风险是风险识别子过程的主要任务,所以选择A