●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.
(71)A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstorming
第1题:
2 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第2题:
85 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk
第3题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第4题:
3 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk
第5题:
● Project tradeoffs are usually made by comparing _____ and constraints.
A Time, cost, and quality
B Time, risk, and quality
C Risk, quality, and manpower availability
D Cost, quality, and technical performance
E Cost, quality, and risk
第6题: