The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

题目

The Estimate Activity Resource process is closely coordinated with the(73) process.

A.Estimate Costs

B.Sequence Activities

C.Plan Communications

D.Conduct Procurements


相似考题
参考答案和解析
正确答案:A
解析:估算活动资源与成本估算是密切联系的。
更多“The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements”相关问题
  • 第1题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第2题:

    Which three statements correctly describe the features of the I/O calibration process?()

    A. Only one I/O calibration process can run at a time.

    B. It automates the resource allocation for the Automated Maintenance Tasks.

    C. It improves the performance of the performance-critical sessions while running.

    D. It can be used to estimate the maximum number of I/Os and maximum latency time for the system.

    E. The latency time is computed only when the TIMED_STATISTICS initialization parameter is set to TRUE.


    参考答案:A, D, E

  • 第3题:

    ( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate,and closing out contracts.

    A、Control Procurements

    B、Conduct Procurements

    C、plan Procurements management

    D、Procurements strategy


    参考答案:A

  • 第4题:

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

    A.Activity list

    B.Work Breakdown Structures

    C.Activity Attributes

    D.Milestone Lists


    正确答案:B

  • 第5题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development


    正确答案:D
    解析:在某些项目,特别是在范围较小的项目中,活动排序、活动资源估算、活动历时估算和进度制定连接得如此紧密,以至于它们被视为可以由一个人在相对较短的时间内执行的单独过程。

  • 第6题:

    Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

    (74)

    A. milestone

    B. baseline

    C. quality

    D. work


    正确答案:D

  • 第7题:

    Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.

    A.work breakdown structure
    B.baseline
    C.software requirements specification
    D.plan

    答案:A
    解析:
    翻译:在项目进度计划制定前,制定者应该有一份工作分解结构,一份针对每个任务的工作量估算,以及可用资源列表。A.工作分解结构 B.基线 C.软件需求说明书 D.计划

  • 第8题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。A. 活动历时估算 制订进度计划 活动的资源估算B. 活动的资源估算 活动历史估算 制订进度计划C. 制订进度计划 活动的资源估算 活动历时估算D. 活动的资源估算 制订进度计划 活动历时估算

  • 第9题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A、time estimating
    • B、cost estimating
    • C、project planning
    • D、schedule development

    正确答案:C

  • 第10题:

    The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

    • A、estimating
    • B、defining
    • C、planning
    • D、sequencing

    正确答案:A

  • 第11题:

    Which three statements correctly describe the features of the I/O calibration process?()

    • A、 Only one I/O calibration process can run at a time
    • B、 It automates the resource allocation for the Automated Maintenance Tasks
    • C、 It improves the performance of the performance-critical sessions while running
    • D、 It can be used to estimate the maximum number of I/Os and maximum latency time for the system
    • E、 The latency time is computed only when the TIMED_STATISTICS initialization parameter is set to TRUE

    正确答案:A,D,E

  • 第12题:

    单选题
    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
    A

    activity duration estimating, schedule developing, activity resource estimating

    B

    activity resource estimating, activity duration estimating, schedule development

    C

    schedule developing, activity resource estimating, activity duration estimating

    D

    activity resource estimating, schedule developing, activity duration estimating


    正确答案: A
    解析: 暂无解析

  • 第13题:

    The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing


    正确答案:A
    解析:估算活动历时的过程会用到活动工作范围、所需资源类型、估计的资源数量以及建立在资源可用性上的资源日历等信息。

  • 第14题:

    What is the state of a process if a resource is not available? (Intel)


    正确答案:
                

  • 第15题:

    On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.project planning

    B.time estimating

    C.cost estimating

    D.schedule development


    正确答案:D

  • 第16题:

    passive activity. ____73_______


    正确答案:
    E

  • 第17题:

    The Estimate Activity Resource process is closely coordinated with the (73)process.

    (73)

    A. Estimate Costs

    B. Sequence Activities

    C. Plan Communications

    D. Conduct Procurements


    正确答案:A

  • 第18题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。(71) A.活动历时估算 制订进度计划 活动的资源估算 B.活动的资源估算 活动历史估算 制订进度计划 C.制订进度计划 活动的资源估算 活动历时估算 D.活动的资源估算 制订进度计划 活动历时估算

  • 第19题:

    The Estimate Activity Resource process is closely coordinated with the ( ) process.

    A.Estimate Costs
    B.Sequence Activities
    C.Plan Communications
    D.Conduct Procurements

    答案:A
    解析:

  • 第20题:

    Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

    • A、milestone
    • B、baseline
    • C、quality
    • D、work

    正确答案:D

  • 第21题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第22题:

    The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    • A、estimating
    • B、defining
    • C、planning
    • D、sequencing

    正确答案:D

  • 第23题:

    多选题
    Which three statements correctly describe the features of the I/O calibration process?()
    A

    Only one I/O calibration process can run at a time.

    B

    It automates the resource allocation for the Automated Maintenance Tasks.

    C

    It improves the performance of the performance-critical sessions while running.

    D

    It can be used to estimate the maximum number of I/Os and maximum latency time for the system.

    E

    The latency time is computed only when the TIMED_STATISTICS initialization parameter is set to TRUE.


    正确答案: B,C
    解析: 暂无解析