67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual
B. Development.
C. Execution
D. Finish
E. All of the above
第2题:
6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第3题:
82 Which of the following are included in the Acquisition phase(s) of the project life cycle.
A. concept and development
B. development and planning
C. execution and phase-out
D. planning and implementation
E. concept and planning
第4题:
● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
第5题:
In which phase of the software engineering process is the Software Requirements Specification developed?
A. definition phase
B.engineering
C.maintenance
D.development phase
第6题:
As an important phase in software development, software design is the continuation of software requirement analysis phasE.
Ⅰ.software structure
Ⅱ.software procedure
Ⅲ.software module
Ⅳ.software document
which of the following should be included in software design phase?
A.Ⅰand Ⅱ
B.Ⅱand Ⅲ
C.Ⅰ,Ⅱ and Ⅲ
D.All
第7题:
● Consumption of the total life-cycle effort in software maintenance is (71) that in software development.
(71)
A.less than
B.larger than
C.equal or less than
D.equal or larger than
第8题:
Consumption of the total life-cycle effort in software maintenance is(71)that in software development.
A.less than
B.larger than
C.equal or less than
D.equal or larger than
第9题:
Which of the following statements is correct?
A.The definition phase results in the Software Requirements Specification.
B.Testing is optional in software life cycle.
C.CASE tools can only aid in the design phase of a software life cycle.
D.A change during a later phase does not require the documentation of all earlier phases to be updated.
第10题:
第11题:
第12题:
activity
procedure
process
progress
第13题:
141 Feasibility studies occur in which life cycle phase (s)?
A. Conceptual
B. Conceptual or Development
C. Execution
D. Preliminary planning
E. any life cycle phase
第14题:
88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B. Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第15题:
● Feasibility studies occur in which life cycle phase (s)?
A Conceptual
B Conceptual or Development
C Execution
D Preliminary planning
E any life cycle phase
第16题:
●In which phase of the software engineering process is the Software Requirements Specification developed? (68) .
(68) A.development phase
B.engineering phase
C.maintenance phase
D.Definition phase
第17题:
●As an important phase in software development,software design is the continuation of software requirement analysis phase. (69) .
Ⅰ.software structure
Ⅱ.software document
Ⅲ.software module
Ⅳ.software procedure
Which of the following should be included in software design phase?
(69) A.Ⅱ andⅢ
B.Ⅰ andⅡ
C.Ⅰ,Ⅱ andⅢ
D.All
第18题:
Software document is an important part of software and a basis of software's development phase.It also influnces software's
A.Reusability
B.Maintanence
C.Expansibility
D.Portability
第19题:
Which phase of the software development requires the most development time?
A.the design phase
B.the testing phase
C.the maintenance phase
D.the development phase
第20题:
The stages within the development phase of the software life cycle are ( 71 ).
A.design, analysis, implementation, and testing
B.analysis, design, implementation, and testing
C.analysis, design, testing, and implementation
D.design, analysis, testing, and implementation
第21题:
第22题: