The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . A.Chang control board B.Project management office C.Project manager D.Configuration management officer

题目
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer

相似考题
参考答案和解析
答案:C
解析:
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。
更多“The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . ”相关问题
  • 第1题:

    Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A . Project Engineer

    B . Project Manager

    C . Functional Manager

    D . Quality Assurance Manager

    E . Project Owner


    正确答案:B

  • 第2题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第3题:

    105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B. Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第4题:

    ● A comprehensive definition of scope management would be:

    A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.

    B Approval of the scope baseline.

    C Approval of the detailed project charter.

    D Configuration control.

    E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.


    正确答案:A

  • 第5题:

    The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.

    ①A.resource manager

    B.division manager

    C.functional manager

    D.project manager

    ②.A.quality management

    B.configuration management

    C.project manager

    D.scope management


    参考答案:D,D

  • 第6题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第7题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第8题:

    The perform Integrated Change Contorl process is the uitimste responsbilityof the (请作答此空) ,Although changes my be intitated verbally,they should be recorded in writtern form and entered into the ( ) syste.

    A.resource manager
    B.division manager
    C.functional manager
    D.projeet manager

    答案:D
    解析:
    翻译:执行综合变更控制过程是(请作答此空)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入( )系统。A. 资源管理员B. 部门经理C. 职能经理D. 项目经理

  • 第9题:

    The perform Integrated Change Contorl process is the uitimste responsbilityof the(请作答此空),Although changes my be intitated verbally,y they should be recorded in writtern form and entered into the( )syste.

    A.resource sanager
    B.division sanager
    C.functional manager
    D.projeet manager

    答案:D
    解析:
    执行综合变更控制过程是(73)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入(74)系统。(73)A.资源管理员B.部门经理C.职能经理D.项目经理
    (74)A.质量管理B.配置管理C.风险管理D.范围管理

  • 第10题:

    The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.

    A.Cost control
    B.Schedule control
    C.Change control
    D.Risk control

    答案:C
    解析:
    项目管理计划定义了项目是如何执行、监控和控制以及关闭的。它是由整体变更控制对流程进行控制和批准的。

  • 第11题:

    ( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

    A.Integrated management
    B.Configuration management
    C.Scope management
    D.Requirements management

    答案:D
    解析:
    需求管理是一个记录的过程。对需求进行分析、描绘、划分优先顺序,达成需求并控制其变化、并传达给利益相关者,它在项目中是一个持续的过程。

  • 第12题:

    单选题
    Ravi, like many project (1) , had studied the waterfall model of software development as the primary software life-cycle (2) . He has all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (3) and not as (4) . The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice. To be the most situation, an existing process must be (5) to the new problem. A development process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process. 空白(2)处应选择()
    A

    activity

    B

    procedure

    C

    process

    D

    progress


    正确答案: C
    解析: 参考译文:和许多项目经理一样,Ravi研究了作为主要软件生命周期过程的瀑布模型。他打算在首个任务,也就是即将开始的项目中使用瀑布模型。但是,他发现瀑布模型不能满足要求,原因是客户希望软件分阶段交付,也就意味着系统必须一部分一部分地交付和构建,而不是作为一个整体进行。这种情况在很多其他项目中也类似。现实世界中,很难有一种标准的过程或在前期的项目中使用的过程作为目前项目的最佳选择。对于大部分情况,必须对已存在的过程进行调整,以适应新的问题。但是,即使经过调整,一个开发过程也很难处理变化的需求。为了适应变化的需求而不失去对项目的控制,你必须用需求变更管理过程从而对开发过程进行补充。

  • 第13题:

    41 In the project environment, the individual ultimately responsible for quality control is:

    A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D. The project manager who has ultimate responsibility for the entire project.

    E.the customer who must ensure that he is receiving a quality product from the vendor


    正确答案:D

  • 第14题:

    23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第15题:

    ● Scope management is:

    A a project control function.

    B employs change control.

    C a work authorization process.

    D considers Cost, Quality and Schedule.

    E All of the above.


    正确答案:E

  • 第16题:

    ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

    (73) A. change the scope baseline

    B. contact the customer to determine if the change adds value

    C. call a meeting of the change control board

    D. change the project' s objectives


    正确答案:B

  • 第17题:

    Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).

    A.change the scope baseline

    B.contact the customer to determine if the change adds value

    C.call a meeting of the change control board

    D.change the project’s objectives


    正确答案:C
    项目经理相信调整范围能为客户增加收益,项目经理应该(73)。A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。

  • 第18题:

    The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

    A.change control board

    B. project management office

    C.project manager

    D.configuration management officer


    正确答案:C
    本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。

  • 第19题:

    Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )


    A.change the scope baseline
    B.contact the customer to determine if the change adds value
    C.call A.meeting of the change control board
    D.change the project's objectives


    答案:C
    解析:
    项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。

  • 第20题:

    The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。

    A.Chang control board变更控制委员会
    B.Project management office项目管理办公室
    C.Project manager项目经理
    D.Configuration management officer配置管理员

    答案:C
    解析:

  • 第21题:

    ( )is not included in Perform Integrated Change Control Process.

    A.Defining subsidiary plans
    B.Approving changes
    C.Managing changes to deliverables
    D.Reviewing all change requests

    答案:A
    解析:
    执行变更控制过程中不包括定义附属计划。

  • 第22题:

    When required the perform Integrated Change Control Process includes ()Which is a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for ing and communicating such decisions

    A.BBC]
    B.CCB]
    C.BCB]
    D.CBC]

    答案:B
    解析:
    当需要时变更时,要执行综合变更控制过程,CCB(变更控制委员会)是一个正式被授权的组织,负责审查批准、推迟或拒绝项目变更,并负责制定和传达该决定。

  • 第23题:

    ( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

    • A、Integrated management
    • B、Configuration management
    • C、Scope management
    • D、Requirements management

    正确答案:D