第1题:
19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A. Direct labor dollars
B. Direct labor hours.
C. Overhead rates.
D. Procurement costs.
E. None of the above
第2题:
170 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D. cannot be quantified for first time projects.
E. B or D
第3题:
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第4题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第5题:
Eventually, they gave up the project to build a bridge over the river because of the _______ high costs it would involve.
A:excessively
B:expensively
C:effectively
D:efficiently
第6题:
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
第7题:
第8题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
第9题:
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
第10题:
Bandwidth that is reserved for SVCs to route over a trunk
Bandwidth that is reserved on a trunk so that ABR connections can burst
Bandwidth on a trunk that is reserved for control traffic and cannot be used by connections
Bandwidth that cannot be allocated to connections but can be used to accommodate statistical variations in the traffic
第11题:
skip over
sit upon
give in to
smooth away
第12题:
a language of business
your sales figures, your costs, and your profits
Both A and B
第13题:
28 The reason that cost management is so difficult in project management is that:
A. Projects by definition and nature are non-recurring events and are therefore difficult to predict.
B .There are no tools for identifying project tasks.
C. Project managers do not care about tracking costs, as only schedules are important to all project managers.
D. A and B only
E. B and C only
第14题:
A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix
第15题:
involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
A.Metrics
B.Measurement
C.Benchmarking
D.Baseline
第16题:
Eventually最终, they gave up the project to build a bridge over the river because of the _______ high costs it would involve.
A:excessively 过分地,极度
B:expensively
C:effectively
D:efficiently 高效的
第17题:
An application software is any program(68)to perform. a specific function directly for the user or, in some cases, for another application program.
A.design
B.designing
C.designed
D.praticed
第18题:
The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……
A.Monitoring
B.Managing
C.Gathering
D.Reducing
第19题:
第20题:
Within Information Technology projects, communications between the project manager and the project team members should take place:()
第21题:
performance
process
product
object
第22题:
by written and oral communication.
via a weekly status report.
through the formal chain of command.
with approved template forms.
第23题:
Strongmatrix
Projectized
Projectcoordinator
Weakmatrix