第1题:
In a matrix organizational form, MBO may be difficult to implement:
A . If the functional employees are supervised closely by the line manager rather than the project manager
B . Unless the project manager has an input into the employee's performance review
C . Unless the project and line managers agree on the ultimate objective
D . Unless the project and line managers agree to the duration of the task
E . None of the above are correct answers
第2题:
The way a project manager sends and receives information depends upon:
A How others relate to the project manager
B The project manager's level in the organizational hierarchy
C the size and nature of the project
D the project manager's salary and age
E the number of projects going on at one time in the company
第3题:
6 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A. Increase, increase.
B. Increase, decrease.
C. Decrease, decrease.
D. Decrease, increase.
E. Remain the same, return to customer
第4题:
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A. Change the scope baseline
B. Prepare a variance report
C. Call a meeting of the configuration control board
D. Change the project's objectives
E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第5题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第6题:
● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).
(75)
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第7题:
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第8题:
●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .
(72)
A. tell the customer that he will not address any problems becausethis is only an information exchange meeting
B. tell the customer that the problem is not sufficiently defined to determine the appropriate action
C. collect as much information on the problem without committing his company to a solution
D. give the customer a range of solutions that might be acceptable to his Company
第9题:
第10题:
第11题:
第12题:
A new IBM x 3650 M3 customer has experienced support issues with problem resolution from their previous vendor. The biggest problem was with Microsoft applications failing intermittently. Which of the following IBM products covers this issue?()
第13题:
The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:
A . Proposed salary increases if the project is successful
B . Bonuses for early completion date
C . A promise of future assignments
D . Well-defined project objectives
E . Linear responsibility charts
第14题:
108 The way a project manager sends and receives information depends upon:
A. How others relate to the project manager
B. The project manager's level in the organizational hierarchy
C. the size and nature of the project
D. the project manager's salary and age
E. the number of projects going on at one time in the company
第15题:
41 In the project environment, the individual ultimately responsible for quality control is:
A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D. The project manager who has ultimate responsibility for the entire project.
E.the customer who must ensure that he is receiving a quality product from the vendor
第16题:
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第17题:
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第18题:
● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .
(73) A. change the scope baseline
B. contact the customer to determine if the change adds value
C. call a meeting of the change control board
D. change the project' s objectives
第19题:
●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).
(71)
A.periodic project reports, periodic visits to the customer, and telephonic exchanges
B.subordinates, project team members, and the project sponsor
C.one-time reports, weekly reports, and monthly reports
D.the telephone, facsimile, and data transmission
第20题:
Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project’s objectives
第21题: