第1题:
The way a project manager sends and receives information depends upon:
A How others relate to the project manager
B The project manager's level in the organizational hierarchy
C the size and nature of the project
D the project manager's salary and age
E the number of projects going on at one time in the company
第2题:
11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A. Reduce features and/or functionality
B Increase risk.
C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D. All of the above.
E. A and B only
第3题:
● The difference between a project and a program is that:
A A program is made up of multiple projects
B A program requires at least three times longer to plan than a project
C A project is a one-shot deal while a program is on-going
D A and C
E B and C
第4题:
The(70)provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
第5题:
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM
第6题:
The( )provides the project manager with the authority to apply organizational resources to project activities。
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第7题:
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
第8题:
第9题:
第10题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第11题:
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(1)处填()
第12题:
Benchmarking
Quality metric
Quality checklist
Brainstorming
第13题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第14题:
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
第15题:
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM
第16题:
is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A.PDM
B.CPM
C.PERT
D.AOA
第17题:
The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders
第18题:
The (73) provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第19题:
In project time management processes,( )involves identifying and documenting the relationships between project activities.
A.activity definition
B.activity sequencing
C.schedule control
D.Schedule development
第20题:
第21题:
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()
第22题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第23题:
Benchmarking
Quality metric
Quality checklist
Brainstornung