In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.
A.10
B.45
C.50
D.100
第1题:
Project(29)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
第2题:
Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
第3题:
第4题:
Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
第5题:
第6题: