A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。
第1题:
2 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第2题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第3题:
第4题:
28 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A. Time, schedule and cost.
B. Management coordination and organization structuring.
C. Work methods and accountability.
D. Quality of work.
E. Risk and impact decision-making
第5题:
A.Completed,Deposited,Released,Shipped
B.Completed,Released,Shipped,Deposited
C.Deposited,Released,Shipped,Completed
D.Released,Shipped,Completed,Deposited
E.Released,Shipped,Deposited,Completed
第6题:
文化产业项目工作分解结构(work_breakdown_structure,WBS)是文化产业项目范围定义中给出的项目工作范围的描述文件。