参考答案和解析
参考答案:正确
更多“Polysemy is concerned with words of more than one meaning.() ”相关问题
  • 第1题:

    No navigational aids are shown and the chart is not kept corrected for alterations in depths inside the pecked lines. For more detailed information,the larger scale charts must be ______.

    A.referred to

    B.appreciated

    C.met with

    D.concerned


    正确答案:A

  • 第2题:

    The ambiguity in "My friend drove me to the bank." is caused by__________.

    A.lexical items
    B.a grammatical structure
    C.homonymy
    D.polysemy

    答案:D
    解析:
    考查语义学知识。一词多义(polysemy)经常会导致表达含糊不清,表达意思不清楚。本句的歧义在于不知道是开车带“我”去河边还是去银行.

  • 第3题:

    I'm content with the way the campaign has gone.

    A:tied
    B:satisfied
    C:filled
    D:concerned

    答案:B
    解析:

  • 第4题:

    The ambiguity in "My friend drove me to the bank." is caused by__________.

    A. lexical items
    B. a grammatical structure
    C. homonymy
    D. polysemy

    答案:D
    解析:
    考查语义学知识。一词多义(polysemy)经常会导致表达含糊不清,表达意思不清楚。本句的歧义在于不知道是开车带“我”去河边还是去银行.

  • 第5题:

    The ambiguity in "My friend drove me to the bcmk." is caused by

    A.lexical items
    B.a grammatical structure
    C.homonymy
    D.polysemy

    答案:D
    解析:
    考查语义学知识。一词多义(polysemy)经常会导致表达含糊不清,表达意思不清楚。本句的歧义在于不知道是开车带“我”去河边还是去银行。

  • 第6题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。