A、通过安排项目进度、减少资源时间,来处理资源的有效使用
B、一般情况下可能对活动历时没有影响
C、可能延长原始项目完成日期
D、A与C
第1题:
171 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第2题:
53 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第3题:
【单选题】下面哪个说法正确?
A.库存可以平衡客户资源也可以平衡生产资源
B.库存可以平衡客户资源但不能平衡生产资源
C.库存不能平衡客户资源但可以平衡生产资源
D.库存即不能平衡客户资源也不能平衡生产资源
第4题:
116 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.
B. Manpower leveling.
C. Resource limited planning.
D. Manpower planning.
E. Manpower contingency planning.
第5题:
● Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D