更多“Shipboard Oil Pollution Emergency Plan shall be carried on board by ______.A.Oil tankerB.B ”相关问题
  • 第1题:

    Certificate of Fitness for the Carriage of Liquefied Gases in Bulk shall be carried on board by ______.

    A.gas carriers constructed on or after 1 July 1986

    B.gas carriers constructed before 1 July 1986

    C.All chemical tankers

    D.oil tankers of 150 gross tonnage and above


    正确答案:B

  • 第2题:

    Oil Record Book shall be carried on board by ______ which is engaged in voyages to ports or offshore terminals under the jurisdiction of other Parties to MARPOL 73/78.

    A.Oil tanker

    B.Bulk carrier of 400 gross tonnage and above

    C.Container vessel

    D.Passenger ship


    正确答案:B

  • 第3题:

    International Certificate of Fitness for the Carriage of Dangerous Chemicals in Bulk shall be carried on board by ______.

    A.chemical tankers constructed on or after 1 July 1986

    B.chemical tankers constructed before 1 July 1986

    C.All chemical tankers

    D.oil tankers of 150 gross tonnage and above


    正确答案:A

  • 第4题:

    Formulation and exercise of emergency response plan is carried out in( ) phase.


    A .planning and design
    B. deployment and implementation
    C. operation management
    D. continuous improvement


    答案:B
    解析:
    应急预案的制定和实施( )阶段。A.计划和设计 B.部署和实施C.运营管理 D.持续改进

  • 第5题:

    单选题
    A ship that,at any time,operates seaward of the outermost boundary of the territorial sea is required to prepare,submit,and maintain a(n)().
    A

    synthetic plastic discharge plan

    B

    oil discharge plan

    C

    shipboard oil pollution emergency plan

    D

    vapor recovery procedures plan


    正确答案: C
    解析: 暂无解析

  • 第6题:

    单选题
    The shipboard oil pollution emergency plan will be invalid after ()
    A

    one year

    B

    two years

    C

    four years

    D

    five years


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    A shipboard oil pollution emergency plan is required of ().
    A

    all vessels, regardless of size and commercial application

    B

    any barge or other ship which is constructed or operated in such a manner that no oil in any form can be carried aboard

    C

    an oil tanker of 150 gross tons or above, or other ship of 400 gross tons or above

    D

    an oil tanker of 400 gross tons and above, or other ships of 150 gross tons and above


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    The Pollution Prevention Regulations require that all oil spills in United States water be reported immediately to the ().
    A

    local port authority

    B

    Corps of Engineers

    C

    USCoast Guard

    D

    state pollution board


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    Shipboard Oil Pollution Emergency Plans must be reviewed().
    A

    annually by the owner,with a letter submitted six months before expiration

    B

    only once every five years,with a letter submitted six months before expiration

    C

    and the entire plan resubmitted for approval once every five years,six months before expiration

    D

    annually by the owner,with a letter submitted to the Coast Guard within one month of the anniversary date of the plan approval


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    Which is a mandatory section of the shipboard Oil Pollution Emergency Plan().
    A

    Reporting requirements

    B

    Removal equipment list

    C

    Planned exercises

    D

    List of individuals required to respond


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    Which list is NOT required to be provided as part of the appendices of the Shipboard Oil Pollution Emergency Plan?()
    A

    A list of agencies or officials of Coastal State Administrators responsible for receiving and processing incident reports

    B

    A list of agencies or officials in regularly visited ports

    C

    A list specifying who will be responsible for informing the parties listed and the priority in which they must be notified

    D

    A list of personnel duty assignments


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    When amendments are made to the Shipboard Oil Pollution Emergency Plan,the revisions must be submitted to the Coast Guard().
    A

    one month before the anniversary date of the plan

    B

    six months before the end of the approval period

    C

    and cannot be implemented without approval

    D

    and can be implemented without immediate approval as long as final approval is received within six months of submission


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Certificate of insurance or other financial security in respect of civil liability for oil pollution damage shall be carried on board by ______.

    A.ships carrying more than 2000 tons of oil in bulk as cargo

    B.oil tankers

    C.bulk chemicals carriers

    D.liquefied gas carriers


    正确答案:A

  • 第14题:

    Shipboard Oil Pollution Emergency Plan shall be carried on board by ______.

    A.Oil tanker of 150 gross tonnage and above

    B.Bulk carrier

    C.Container vessel

    D.Passenger ship


    正确答案:A

  • 第15题:

    Which is a mandatory section of the shipboard Oil Pollution Emergency Plan ________.

    A.Reporting requirements

    B.Removal equipment list

    C.Planned exercises

    D.List of individuals required to respond


    正确答案:A

  • 第16题:

    A 35000 ton product oil tanker will be delivered in a few days, as a surveyor, you go on board for finally confirming the documentations required by SOLAS, which shall be equipped on board. Which of them as below are correct:()

    • A、Fire control plan
    • B、Muster list and Emergency procedures
    • C、Nautical publications
    • D、International code of signals and Inmarsat manual
    • E、Training manual

    正确答案:A,B,C,D

  • 第17题:

    多选题
    A 35000 ton product oil tanker will be delivered in a few days, as a surveyor, you go on board for finally confirming the documentations required by SOLAS, which shall be equipped on board. Which of them as below are correct:()
    A

    Fire control plan

    B

    Muster list and Emergency procedures

    C

    Nautical publications

    D

    International code of signals and Inmarsat manual

    E

    Training manual


    正确答案: C,A
    解析: 暂无解析

  • 第18题:

    单选题
    What type of oil is not covered in the oil pollution law?()
    A

    mineral oil

    B

    machinery oil being transferred for shipboard use

    C

    crude oil unrefined

    D

    normal bilge oil and water


    正确答案: A
    解析: 暂无解析

  • 第19题:

    单选题
    A shipboard Oil Pollution Emergency Plan is required of().
    A

    all vessels,regardless of size and commercial application

    B

    any barge or ship constructed or operated in such a manner that no oil in any form can be carried aboard

    C

    an oil tanker of 150 gross tons and above,or other ship of 400 gross tons and above

    D

    an oil tanker of 400 gross tons and above,or other ships of 150 gross tons and above


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    The pollution prevention regulations do not apply to the transfer or discharge of ()
    A

    bunker fuel for use aboard ship

    B

    lubricating oil for use aboard ship

    C

    coconut oil carried in tank vessels

    D

    oily water from a ships bilges


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    The approval period for a shipboard Oil Pollution Emergency Plan expires after().
    A

    two years

    B

    three years

    C

    four years

    D

    five years


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    Shipboard Emergency Drills must be carried out at least()on board cargo ship.
    A

    Once every third year

    B

    Once a month

    C

    Once a year

    D

    Once a week


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    After an occurrence of oil pollution,what shall be done first by a vessel in Chinese port? ().
    A

    use oil dispersion agent and wait for investigation

    B

    try to collect the oil on deck or in water

    C

    report to Harbor Master

    D

    B and C


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    In the case of new crude oil tankers,the additional ballast permitted shall be carried in cargo tanks only if such tanks have been()before departure from an oil unloading port or terminal.
    A

    inerted

    B

    crude oil washed

    C

    diluted

    D

    cleaned


    正确答案: B
    解析: 暂无解析