Which of the following is the stated proper sequence before commencing cargo operations aboard Ro-Ro vessels?
A.Start ventilation,lower the ramp,notify engine room
B.Lower the ramp,start ventilation,notify engine room
C.Notify engine room,lower the ramp,start ventilation
D.Start ventilation,notify engine room,lower the ramp
第1题:
Which safety precaution(s)should be observed during crane operations ________.
A.Checking for proper lifting from beneath the load during cargo operations
B.Using the proper slings or other lifting devices during cargo operations
C.Relaying communications to port agents on the pier during cargo hoists
D.All of the above
第2题:
During the planning stage of cargo operations,stress and displacement calculations should be carried out at incremental steps commensurate with the number of _____ and loading sequence of the proposed operation.
A.coefficient of loading
B.stowage factors
C.orders
D.pours
第3题:
第4题:
第5题:
第6题:
Which of the following is not dangerous cargo?()
第7题:
Which of the following privileges permits a user to update the comment on a sequence?()
第8题:
remove an existing list that would slow down cargo operations
initiate loading in conjunction with unloading at the hatch
improve stability during cargo operations
allow longshoremen easy access to the hatch
第9题:
Any internal transfer of oil cargo during a voyage
The discharge overboard in port or at sea of any bilge water accumulated in machinery spaces
The loading or unloading of any or all oil cargo
All of the above
第10题:
Duration of the voyage
Types of cargo units and vehicles to be carried
Weight of cargo units and vehicles
All of the above
第11题:
de′ fend
a′bove
′window
′excuse
第12题:
'frivolous
fri'volous
frivo'lous
frivolou's
第13题:
______ include goods,wares,merchandise,and articles of every kind whatsoever except live animals and cargo which by the contract of carriage is stated as being carried on deck and is so carried.
A.Goods
B.Things
C.Items
D.Articles
第14题:
By regulation,cargo tank atmosphere must be inert before and during which operation ________.
A.Stripping
B.Loading
C.Cleaning
D.All of the above
第15题:
第16题:
第17题:
An administrator installed new components on a server. After the device installation, two of the components fail.Which of the following is the cause of the problem?()
第18题:
Which of the following is a feature of a unit of work?()
第19题:
Start ventilation,lower the ramp,notify engine room
Lower the ramp,start ventilation,notify engine room
Notify engine room,lower the ramp,start ventilation
Start ventilation,notify engine room,lower the ramp
第20题:
The server was not powered off correctly.
The proper ESD procedures were not used.
The devices were installed in the incorrect sequence.
The devices are incompatible with the system.
第21题:
It applies to a single data server.
It is a recoverable sequence of operations.
Its value can be queried from the system catalog tables.
It begins when the application connects to the data server.
第22题:
Stripping
Loading
Cleaning
All of the above
第23题:
Lower the stern ramp,raise/open the stern door,turn on ventilation for cargo holds
Turn on ventilation for cargo holds,raise/open the stern door,lower the stern ramp
Turn on ventilation for cargo holds,lower the stern ramp,raise/open the stern door
Raise/open the stern door,lower the stern ramp,turn on ventilation for cargo holds