Which statement is TRUE concerning protection of double bottom tanks against excessive pressure?
A.Each vent for the tank must be equal to the area of the tank filling line
B.The tanks must be protected by overflows
C.The total area of the vents or the overflow shall be at least equal to the area of the fill line
D.There must be twice as much vent area as the area of the fill line
第1题:
You are loading a cargo tank on your container ship. The tank displays the red label shown. Which statement is TRUE?
A.The tank contains propylene
B.The tank's volume is 1077 cubic feet
C.There are three tanks in the shipment
D.The tank contains an oxidizing material
第2题:
Which operation may cause the pressure in an inert tank to fall below the prescribed limits ________.
A.Loading
B.Discharging
C.Crude oil washing
D.Steaming tanks
第3题:
Which statement is TRUE concerning cargo hose on tank barges ________.
A.Cargo hose must be able to withstand the shut-off head plus the static head of the cargo pump
B.Cargo hose must be able to withstand the static head of the cargo pump but no less than 100 psi
C.Cargo hose must be able to withstand the shut-off head less the static head of the cargo pump but no less than 100 psi
D.Cargo hose must be able to withstand at least 150 psi
第4题:
a service tank
a settling tank
an expansion tank
a double bottom tank
第5题:
oil from flowing out of the tank vent
air from entering the tank vent
vapors from leaving the tank vent
flames on deck from entering the tank vent
第6题:
Primer is used for sea water tanks and double bottom tanks.
Cement wash is used for fresh water tanks and double bottom tanks.
Varnish is used for fresh water tanks and double bottom tanks.
Bitumen is used for fresh water tanks and double bottom tanks.
第7题:
Washing water should be recirculated if possible because it has the same electric potential as the cargo tank being cleaned
The hoses to portable cleaning machines should be disconnected before the machines are removed from the tank
The principal hazard with steaming cargo tanks is raising the ambient temperature above the flame point of the cargo residue
Steam cleaning and water washing are both capable of generating electrostatic charges within a tank
第8题:
gooseneck vents and flame screens
pressure-vacuum relief valves
branch vent lines and a vent header
forced draft blowers
第9题:
Each vent for the tank must be equal to the area of the tank filling line
The tanks must be protected by overflows
The total area of the vents or the overflow shall be at least equal to the area of the fill line
There must be twice as much vent area as the area of the fill line
第10题:
double bottoms
cofferdam
navigating bridge
superstructure
第11题:
only when fully loaded
if one or more tanks are full
when transferring cargo
only when the barge is being towed
第12题:
The tank lie above the waterline and are filled
The tank are partically filled with dry cargo
The tanks are partially filled with liquid cargo
The tanks are filled and lie below the waterline
第13题:
A loaded hopper barge with independent tanks has a placard,with alternating red and white quadrants,on each side and end.Which statement concerning this barge is TRUE ________.
A.The cargo will spontaneously ignite if released to the atmosphere
B.You must operate this barge as a lead barge
C.The barge should be spotted as far away from the towboat as possible
D.The barge must be in a protected position within the tow
第14题:
Regulations require that cargo tanks carrying grades D or E liquids on tank barges be vented with ______.
A.Gooseneck vents and flame screens
B.Pressure-vacuum relief valves
C.Branch vent lines and a vent header
D.Forced draft blowers
第15题:
You are on a tanker designed to carry molten sulfur.Which statement is TRUE ________.
A.There must be two portable toxic vapor detectors on board
B.The cargo tank ventilation system must maintain the H2S vapor concentration at 1.85% or more by volume
C.Cargo temperature may be taken by portable thermometers
D.The pressure in the heating coils in the tanks must be less than that of the cargo exerted on them
第16题:
a service tank
a collecting tank
a sump
a settling tank
第17题:
one meter from the tank bottom and one meter below the tank top
one half the ullage of the tank and one meter below the tank top
one half the ullage of the tank and one meter above the tank bottom
at three meter intervals from the tank top to the bottom
第18题:
Hose connections to the tank must be made with a minimum of three bolts
There must be water pressure on the fire main
You must shut down if another vessel comes alongside
If transferring at anchor,you must display a red flag by day and a red light at night
第19题:
one meter from the tank bottom and one meter below the tank top
one half the ullage of the tank and one meter below the tank top
one half the ullage of the tank and one meter above the tank bottom
at three meter intervals from the tank top
第20题:
gas freed
inerted
filled with water
all of the above as necessary
第21题:
landing area and sources of vapor ignition
main deck
engine room
drill floor
第22题:
close the tank filling valves quickly
top off all tanks at the same time
rill completely all tanks to less than 95% full
reduce the loading rate when topping off
第23题:
Loading
Discharging
Crude oil washing
Steaming tanks