单选题A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and 

题目
单选题
A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()
A

e-Config

B

System Planning Tool (SPT)

C

IBM Workload Estimator (WLE)

D

IBM Performance Monitor (PM)


相似考题
更多“单选题A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and ”相关问题
  • 第1题:

    A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility.  Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()

    • A、 PowerVM Standard Edition on POWER6 hardware
    • B、 PowerVM Standard Edition with POWER5 hardware 
    • C、 PowerVM Enterprise Edition with POWER6 hardware
    • D、 PowerVM Enterprise Edition with POWER5 hardware

    正确答案:C

  • 第2题:

    What current IBM resource can be used for simple-to-complex configurations and can be exported in different formats for the pricing of System x, BladeCenter and System x storage products?()

    • A、System x Sales Configuration Aid (xSCA)
    • B、Standalone Solutions Configuration Tool (SSCT) 
    • C、Configuration & Options Guide - (COG)
    • D、ServerProven

    正确答案:B

  • 第3题:

    A customer would like to see the components needed to perform an upgrade on their DS5100system and get a list price of the cost. What tool can the storage specialist use to generate thisdocument?()

    • A、eConfig
    • B、IBM Blue Horizon
    • C、Standalone Solution Configuration Tool (SSCT)
    • D、Configuration Management Version Control (CMVC)

    正确答案:A

  • 第4题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()

    • A、What are Disaster Recoveryplans
    • B、What are plans for datamigration
    • C、What storage system space isavailable
    • D、DoesiSCSI meet the needs

    正确答案:B

  • 第5题:

    Which command do you issue to upgrade the current software on Junos devices?()

    • A、request system software replace
    • B、request system software install
    • C、request system software add
    • D、request system software upgrade

    正确答案:C

  • 第6题:

    单选题
    A customer has one mainframe and ten open system servers in their current environment. They plan to add the servers to an IBM DS8700 system with four array sites.  How many extent pools should be created to provide the best resource utilization of the DS8700()
    A

    1

    B

    2

    C

    4

    D

    6


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()
    A

    e-Config

    B

    System Planning Tool (SPT)

    C

    IBM Workload Estimator (WLE)

    D

    IBM Performance Monitor (PM)


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()
    A

    e-Config

    B

    System Planning Tool (SPT)

    C

    IBM Workload Estimator (WLE)

    D

    IBM Performance Monitor (PM)


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    Your computer runs Microsoft Windows XP Professional. The computer also runs 20 third-party applications. You plan to upgrade your computer to Microsoft Windows Vista.  The functionality of the existing 20 applications must be maintained even after you upgrade your computer.  You need to ascertain whether the hardware and software on the Windows XP Professional computer will support the upgrade.  What should you do?()
    A

    Run the mbsacli.exe command.

    B

    Run the winnt32.exe /checkupgradeonly command.

    C

    Run the Microsoft Windows Vista Upgrade Advisor application.

    D

    Compare the Microsoft Windows XP Professional system hardware against the Microsoft Windows Vista Hardware Compatibility List (HCL).


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()
    A

    What are Disaster Recoveryplans

    B

    What are plans for datamigration

    C

    What storage system space isavailable

    D

    DoesiSCSI meet the needs


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    Which command do you issue to upgrade the current software on Junos devices?()
    A

    request system software replace

    B

    request system software install

    C

    request system software add

    D

    request system software upgrade


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer would like to see the components needed to perform an upgrade on their DS5100system and get a list price of the cost. What tool can the storage specialist use to generate thisdocument?()
    A

    eConfig

    B

    IBM Blue Horizon

    C

    Standalone Solution Configuration Tool (SSCT)

    D

    Configuration Management Version Control (CMVC)


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer has an IBM System Storage DS5000 and needs to add more disk drives to the unit.There is no record of the configuration for this machine. How can the configuration be retrieved soan upgrade can be configured?()

    • A、use Storage Manager to export the system profile
    • B、create a configuration ineConfig and provide proof of purchase
    • C、use the IBM Standalone Systems Configuration Tool (SSCT) to recreate the configuration
    • D、have the customer contact the IBM AAS coordinator to retrieve a copy of the originalconfiguration

    正确答案:A

  • 第14题:

    A customer has asked for a p690 system with the following requirements:   ? 32 1.9ghz processors   ? 128GB of memory   ? 20 fiber adapters   ? 7 network cards   ? 10 LPARs   What is the most appropriate question to ask them in order to build the hardware configuration correctly?()

    • A、What version of AIX is needed?
    • B、Which SWMA offering is needed?
    • C、What kind of network is the system being attached to?
    • D、What kind of memory should be configured on the system?

    正确答案:C

  • 第15题:

    A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()

    • A、Upgrade system firmware to latest level
    • B、Upgrade to AIX 5.3
    • C、Upgrade HMC to version 6.1
    • D、Convert rootvg filesystems to JFS2

    正确答案:B

  • 第16题:

    A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()

    • A、A public internet connection
    • B、All of the Logical Partitions need to be active
    • C、One partition must be configured with Service Authority
    • D、A local Repository must be configured prior to the update

    正确答案:C

  • 第17题:

    Your computer runs Microsoft Windows XP Professional. The computer also runs 20 third-party applications. You plan to upgrade your computer to Microsoft Windows Vista.  The functionality of the existing 20 applications must be maintained even after you upgrade your computer.  You need to ascertain whether the hardware and software on the Windows XP Professional computer will support the upgrade.  What should you do?()

    • A、Run the mbsacli.exe command.
    • B、Run the winnt32.exe /checkupgradeonly command.
    • C、Run the Microsoft Windows Vista Upgrade Advisor application.
    • D、Compare the Microsoft Windows XP Professional system hardware against the Microsoft Windows Vista Hardware Compatibility List (HCL).

    正确答案:C

  • 第18题:

    单选题
    What is the primary objective of the plan phase()
    A

    Assess the existing environments to determine if it can support the proposed system.

    B

    Identify the activities for installing and configuring the equipment at the customer sites.

    C

    Gather high-level solution requirements, and understand the customer business needs an the opportunity.

    D

    Prepare the activities for day-to-day support, management, and monitoring of the newly implemented system.


    正确答案: B
    解析: 暂无解析

  • 第19题:

    单选题
    A customer has an IBM System Storage DS5000 and needs to add more disk drives to the unit.There is no record of the configuration for this machine. How can the configuration be retrieved soan upgrade can be configured?()
    A

    use Storage Manager to export the system profile

    B

    create a configuration ineConfig and provide proof of purchase

    C

    use the IBM Standalone Systems Configuration Tool (SSCT) to recreate the configuration

    D

    have the customer contact the IBM AAS coordinator to retrieve a copy of the originalconfiguration


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer wants to upgrade an existing pSeries system.  In addition to retrieving the IBM configuration records, what else should be done to ensure an accurate upgrade quote is provided?()
    A

    Request that the pSeries technical specialist provide the discount percentage to the customer.

    B

    Run both eConfig and PCRS6000 to ensure that both configurators provide the same upgrade quote.

    C

    Confirm with the customer that the installed inventory accurately reflects what is actually installed.

    D

    Provide options to the customer so they can choose the most appropriate upgrade for their environment.


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility.  Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()
    A

     PowerVM Standard Edition on POWER6 hardware

    B

     PowerVM Standard Edition with POWER5 hardware 

    C

     PowerVM Enterprise Edition with POWER6 hardware

    D

     PowerVM Enterprise Edition with POWER5 hardware


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()
    A

    A public internet connection

    B

    All of the Logical Partitions need to be active

    C

    One partition must be configured with Service Authority

    D

    A local Repository must be configured prior to the update


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    A customer has asked for a p690 system with the following requirements:   ? 32 1.9ghz processors   ? 128GB of memory   ? 20 fiber adapters   ? 7 network cards   ? 10 LPARs   What is the most appropriate question to ask them in order to build the hardware configuration correctly?()
    A

    What version of AIX is needed?

    B

    Which SWMA offering is needed?

    C

    What kind of network is the system being attached to?

    D

    What kind of memory should be configured on the system?


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    A Power Systems customer would like to upgrade their HMC to the latest version of software tosupport a new hardware feature. What resource will help identify dependencies for firmware and system software for their upgrade?()
    A

    ITSO Redbooks

    B

    Facts and Features

    C

    System Planning Tool

    D

    Fix Level Recommendation Tool


    正确答案: A
    解析: 暂无解析