Configure 2 CFFh combination fibre channel / gigabit Ethernet adapters
Configure 1 CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter
Configure 1 CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
Configure 1 CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
第1题:
Your customer has converted from traditional servers to BladeCenter technology and has a requirement for an RSA adapter on a new BladeCenter server. Which of the following options would you use? ()
第2题:
A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()
第3题:
A customer wants to boot from an iSCSI SAN with their IBM BladeCenter infrastructure running Microsoft Windows Server 2000. What is required for the customer to be able to perform this?()
第4题:
A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
第5题:
A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives (2)two physical Microsoft Active Directory Servers (3)twenty-two physical Citrix servers (4)three physical Web servers (5)one physical vCenter server (6)eight vSphere hosts Which configuration minimally satisfies these requirements?()
第6题:
A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
第7题:
Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch
Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch
Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.
The NPIV switch will count against the number of domains in a fabric
第8题:
Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules
Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules
Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules
Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules
第9题:
Remote Supervisor Adapter II (RSA II Slimline)
Management Module, which comes standard on the BladeCenter
Acoustic Attenuation Module
Ethernet NICs
第10题:
Configure 2CFFh combination fibre channel / gigabit Ethernet adapters
Configure 1CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter
Configure 1CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
Configure 1CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
第11题:
4
3
2
8
第12题:
Fibre Channel Expansion Card for each Blade Server
cKVM Card for each Blade Server
iSCSI Expansion Card for each Blade Server
4Gb Modular Flash Drive
第13题:
A customer has a requirement to eliminate single points of failure for an application. They have allocated one Ethernet adapter to each VIO server on the system. Which features of PowerVM and AIX will support the customer requirement?()
第14题:
A BladeCenter H customer is asking for concurrent Keyboard/Video/Mouse. Select the items required to accomplish this. ()
第15题:
A customer is evaluating using the PCIe SSD adapter for the system boot in their new Power 750. Redundancy and hot-swap capability are required. What configuration supports the customer requirements?()
第16题:
A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()
第17题:
A customer is implementing a POWER Blade solution which requires the VIO Server to be mirrored on internal disk drives. Which Blade supports the requirement?()
第18题:
You can not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch
Using blade servers with the NPIV switch will require more fibre ports on the external fibre switch
Storage devices like Fibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch
The NPIV switch will count against the number of domains in a fabric
第19题:
JS21
JS23
PS700
PS701
第20题:
The FCoE card provides both LAN and fibre channel function from a single card on the blade.
The FCoE advanced technology removes the need for any BladeCenter switching to support this function.
Component reliability on the fibre channel over Ethernet is higher than on regular Ethernet and fibre channel adapters.
The AIX device driver for FCoE has been completely rewritten for the current adapter, eliminating errors and performance issues.
第21题:
4GB Modular Flash Drive for each Blade Server and Dual 15.8GB 2.5 Solid State Drive for each Blade Server
Cisco Intelligent Gb Ethernet Switch Module and IBM BladeCenter Copper Pass-thru Module
Fibre Channel Expansion Card for each Blade Server and Fibre Channel SAN Switch Module
Cisco Intelligent Gb Ethernet Switch Module and Dual 15.8GB 2.5 Solid State Drive for each Blade Server
第22题:
Etherchannel and trunking
Network Interface Backup and Etherchannel
Shared Ethernet Adapter (SEA) Failover and Etherchannel
Network Interface Backup and Shared Ethernet Adapter failover
第23题:
Upgrade the network switches to 10Gb speed.
Install a dual port gigabit Ethernet adapter and configure adapter load balancing teaming with the onboard adapters.
Install one extra adapter to team with the internal adapter and configure adapter failover.
Install two additional NICs and configure adapter load balancing teaming with the onboard adapters.