单选题A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()Avmstat and iostat data from the older m

题目
单选题
A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()
A

 vmstat and iostat data from the older machines

B

 The number of CPUs that were installed in the original machines

C

 Data from Workload Estimator (WLE) and IBM Performance Management (PM)

D

 Performance data that is collected from the new system after it has been put into production


相似考题
参考答案和解析
正确答案: D
解析: 暂无解析