单选题What is the role of the line manager in a project plan?()A Provide resources to a projectB Request requirements changesC Resolve team conflictsD Control the project budget

题目
单选题
What is the role of the line manager in a project plan?()
A

Provide resources to a project

B

Request requirements changes

C

Resolve team conflicts

D

Control the project budget


相似考题
参考答案和解析
正确答案: A
解析: 暂无解析
更多“单选题What is the role of the line manager in a project plan?()A Provide resources to a projectB Request requirements changesC Resolve team conflictsD Control the project budget”相关问题
  • 第1题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第2题:

    In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

    A.Strongmatrix

    B.Projectized

    C.Projectcoordinator

    D.Weakmatrix


    参考答案:B

  • 第3题:

    ● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

    A Change the scope baseline

    B Prepare a variance report

    C Call a meeting of the configuration control board

    D Change the project's objectives

    E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


    正确答案:E

  • 第4题:

    ● Risk management allows the project manager and the project team not to(71).

    (71)

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

    试题(71)分析
      下面不属于风险管理中项目经理和项目团队职责的是  (71)  。
      A.排除大部分项目执行中的风险        B.风险识别
      C.风险分析                          D.妥善处理
    参考答案
    (71)A

  • 第5题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第6题:

    Risk management allows the project manager and the project team not to (71).

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

  • 第7题:

    A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )

    A.assign change tasks to project members
    B.call a meeting of the configuration control board
    C.change the scope baseline
    D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

    答案:D
    解析:
    项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。
    选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
    由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。

  • 第8题:

    ( )is a process developing a document that formally authorizes the existence of a project and provides the
    project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor and Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第9题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.plan Cost Management
    B.Control Cost
    C.Estimate Cost
    D.Determine Budget

    答案:A
    解析:

  • 第10题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第11题:

    In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

    • A、Strongmatrix
    • B、Projectized
    • C、Projectcoordinator
    • D、Weakmatrix

    正确答案:B

  • 第12题:

    单选题
    What is the role of the line manager in a project plan?()
    A

    Provide resources to a project

    B

    Request requirements changes

    C

    Resolve team conflicts

    D

    Control the project budget


    正确答案: D
    解析: 暂无解析

  • 第13题:

    69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

    A. budget, schedule

    B. quality requirements, schedule

    C. size, type of industry

    D. nature, size

    E. project manager, sponsor


    正确答案:D

  • 第14题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第15题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第16题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第17题:

    Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).

    A.change the scope baseline

    B.contact the customer to determine if the change adds value

    C.call a meeting of the change control board

    D.change the project’s objectives


    正确答案:C
    项目经理相信调整范围能为客户增加收益,项目经理应该(73)。A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。

  • 第18题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第19题:

    Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )


    A.change the scope baseline
    B.contact the customer to determine if the change adds value
    C.call A.meeting of the change control board
    D.change the project's objectives


    答案:C
    解析:
    项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。

  • 第20题:

    Risk management allows the project manager and the project team not to()

    A.eliminate most risks during the planning phase of the project
    B.identify project risks
    C.identify impacts of various risks
    D.plan suitable responses

    答案:A
    解析:
    下面不属于风险管理中项目经理和项目团队职责的是(71)。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理

  • 第21题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.Plan Cost Management
    B.Control Cost
    C. Estimate Cost
    D. Determine Budget

    答案:A
    解析:
    ( )的主要好处是它可以指导和指导项目的成本如何在项目中进行管理。A.成本管理计划B.控制成本C.成本估算D.成本预算

  • 第22题:

    ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor anD.Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第23题:

    What is the role of the line manager in a project plan?()

    • A、Provide resources to a project
    • B、Request requirements changes
    • C、Resolve team conflicts
    • D、Control the project budget

    正确答案:A

  • 第24题:

    单选题
    In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
    A

    Strongmatrix

    B

    Projectized

    C

    Projectcoordinator

    D

    Weakmatrix


    正确答案: B
    解析: 暂无解析