单选题If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()A The high level budget estimates are inaccurateB The organizational spendin

题目
单选题
If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()
A

The high level budget estimates are inaccurate

B

The organizational spending plan is inaccurate

C

The budget is not aligned with the spending plan of the organization

D

The detailed bottom up budget will need to be adjusted


相似考题
更多“单选题If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()A The high level budget estimates are inaccurateB The organizational spendin”相关问题
  • 第1题:

    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第2题:

    108 The way a project manager sends and receives information depends upon:

    A. How others relate to the project manager

    B. The project manager's level in the organizational hierarchy

    C. the size and nature of the project

    D. the project manager's salary and age

    E. the number of projects going on at one time in the company


    正确答案:A

  • 第3题:

    30 Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?

    A. Classical / traditional

    B. Pure project

    C. Matrix

    D. Project coordinator

    E. None of the above


    正确答案:C

  • 第4题:

    You are working on the cost budget for one project. Which of the following is true()

    A.This process assigns cost estimates to project activities including risks and contingency plans.

    B.The cost baseline will be used to measure variances and future project performance.

    C.This process assigns cost estimates for expected future period operating costs.

    D.The cost baseline is the expected cost for the project.


    参考答案:B

  • 第5题:

    ● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A task

    B level of effort

    C sub-task

    D project

    E work package


    正确答案:E

  • 第6题:

    ●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.

    (74) A. Contingency reserve

    B. Project profit

    C. Management reserve

    D. Special fund


    正确答案:C

  • 第7题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.plan Cost Management
    B.Control Cost
    C.Estimate Cost
    D.Determine Budget

    答案:A
    解析:

  • 第8题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第9题:

    下列触发切换的原因中, 哪些属于紧急切换()。

    • A、power budget evaluation
    • B、high interference on uplink
    • C、uplink level too low
    • D、uplink quality too low

    正确答案:B,C,D

  • 第10题:

    In the design phase, which service component provides the customer with a comprehensive design? Select exactly 1 answer(s) from the following:()。

    • A、Implementation Plan
    • B、Detailed Design Development
    • C、Project Kick-off
    • D、Staging Plan
    • E、High-Level Design

    正确答案:B

  • 第11题:

    If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

    • A、The high level budget estimates are inaccurate
    • B、The organizational spending plan is inaccurate
    • C、The budget is not aligned with the spending plan of the organization
    • D、The detailed bottom up budget will need to be adjusted

    正确答案:C

  • 第12题:

    单选题
    You are working on the cost budget for one project. Which of the following is true()
    A

    This process assigns cost estimates to project activities including risks and contingency plans.

    B

    The cost baseline will be used to measure variances and future project performance.

    C

    This process assigns cost estimates for expected future period operating costs.

    D

    The cost baseline is the expected cost for the project.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    The way a project manager sends and receives information depends upon:

    A How others relate to the project manager

    B The project manager's level in the organizational hierarchy

    C the size and nature of the project

    D the project manager's salary and age

    E the number of projects going on at one time in the company


    正确答案:A

  • 第14题:

    160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. Matrix

    B. Classical

    C. Expediter

    D. Coordinator

    E. Pure project


    正确答案:E

  • 第15题:

    63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A. task

    B. level of effort

    C. sub-task

    D. project

    E. work package


    正确答案:E

  • 第16题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第17题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第18题:

    The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

    A.Contingency reserve
    B.Project profit
    C.Management reserve
    D.Special fund

    答案:C
    解析:
    项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。

  • 第19题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.Plan Cost Management
    B.Control Cost
    C. Estimate Cost
    D. Determine Budget

    答案:A
    解析:
    ( )的主要好处是它可以指导和指导项目的成本如何在项目中进行管理。A.成本管理计划B.控制成本C.成本估算D.成本预算

  • 第20题:

    You are working on the cost budget for one project. Which of the following is true()

    • A、This process assigns cost estimates to project activities including risks and contingency plans.
    • B、The cost baseline will be used to measure variances and future project performance.
    • C、This process assigns cost estimates for expected future period operating costs.
    • D、The cost baseline is the expected cost for the project.

    正确答案:B

  • 第21题:

    下列触发切换的原因中,哪种不属于紧急切换()

    • A、power budget evaluation
    • B、high interference on uplink
    • C、uplink level too low
    • D、uplink quality too low

    正确答案:A

  • 第22题:

    What is the role of the line manager in a project plan?()

    • A、Provide resources to a project
    • B、Request requirements changes
    • C、Resolve team conflicts
    • D、Control the project budget

    正确答案:A

  • 第23题:

    单选题
    What is the role of the line manager in a project plan?()
    A

    Provide resources to a project

    B

    Request requirements changes

    C

    Resolve team conflicts

    D

    Control the project budget


    正确答案: D
    解析: 暂无解析