Probability-Impact matrix
Pareto chart
R-Chart
PERT (Program Evaluation and Review Technique) analysis
第1题:
By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
第2题:
59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A. Significantly reduce project risks
B. eliminate project risks
C. provide a rational basis for better decision making
D. identify risks, their impact(s), and any appropriate responses
E. None of the above
第3题:
42 Which of the following organizations has the best technical project control?
A. matrix
B. functional
C. projectized
D. B and C
E. A and B
第4题:
A.PERT
B.Resourceleveling
C.Schedulecompression
D.Critical chain method
第5题:
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
第6题:
??Many useful tools and techniques are used in developing schedule.( 73) is a schedule
network analysis technique that modifies the project schedule to account for limited resource
??
A.PERT
B. Resource levelling
C.Schedule compression
D.Critical chain method
第7题:
第8题:
第9题:
第10题:
第11题:
( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
第12题:
PERT
Resourceleveling
Schedulecompression
Critical chain method
第13题:
Which of the following diagrams is most useful in impact analysis:
A arrow diagrams
B precedence diagrams
C decision trees
D Pareto diagrams
E cause and effects diagrams
第14题:
178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
A. Work breakdown structure
B. milestone review and schedule technique
C. cost/schedule control system
D. planning programming budget system
E. program and evaluation review technique
第15题:
98 Which of the following tools and techniques can be used to collect information for the project closure reports?
A. Customer Surveys
B. Brainstorming
C. Document and Performance Analysis
D. Lessons Learned
E. All of the above
第16题:
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
(72)
A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method
第17题:
Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT B.Resource levelling C.Schedule compression D.Critical chain method
第18题:
第19题:
第20题:
第21题:
第22题:
Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
第23题:
Which of the following techniques is used for tracking the project risks?()