Requiring stakeholders to sign-off on project plan components
Requesting input from all stakeholders during the planning process
Providing an open line of communication regarding the project
Clearly illustrating how the project relates to the company’s objectives
第1题:
● The inputs of developing project management plan do not include (72).
(72)
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
第2题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第3题:
The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders
第4题:
The communication management plandetermines the information and communications needs of the stakeholders. In thefollowing statements related to communication management plan, (73) is false.
A.The communication management plan is contained in, or is a subsidiary plan of, the project management plan
B.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project
C.The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baseline
D.The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails
第5题:
Risk management allows the project manager and the project team not to (71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第6题:
第7题:
第8题:
第9题:
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
第10题:
Which is the MOST effective method for generating support for your project plan?()
第11题:
project charter
stakeholder management strategy
project scope statement
outputs from planning processes
第12题:
Benchmarking
Quality metric
Quality checklist
Brainstornung
第13题:
● Risk management allows the project manager and the project team not to(71).
(71)
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第14题:
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第15题:
Your company CEO just sent you an E-mail asking you to make a presentation on your project, which has been in progress for 10 months, to all identified internal and external stakeholders. He scheduled the presentation for next Monday. You expect more than 50 people to atten.The first step in preparing the presentation is to(71).
A.define the audience
B.determine the objective
C.decide on the general form of the presentation
D.plan a presentation strategy
第16题:
● Your company CEO just sent you an E-mail asking you to make a presentation on your project, which has been in progress for 10 months, to all identified internal and external stakeholders. He scheduled the presentation for next Monday. You expect more than 50 people to attend. The first step in preparing the presentation is to__(71)__.
(71)A.define the audience
B.determine the objective
C.decide on the general form. of the presentation
D.plan a presentation strategy
第17题:
Your company CEO just sent you an E-mail asking youto make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend.The first step in preparing the presentation is to ( ).
A.define the audience
B.determine the objective
C.decide on the general form of the presentation
D.plan a presentation strategy
第18题:
第19题:
第20题:
The inputs of developing project management plan do not include()
第21题:
Your company CEO just sent you an E-mail asking you to make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend. The first step in preparing the presentation is to ( ).
第22题:
The communication management plan is contained in or is a subsidiary plan of, the project management plan.
The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
第23题:
Requiring stakeholders to sign-off on project plan components
Requesting input from all stakeholders during the planning process
Providing an open line of communication regarding the project
Clearly illustrating how the project relates to the company’s objectives
第24题:
Benchmarking
Quality metric
Quality checklist
Brainstorming