单选题A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()A Upgrade OS to AIX 5.2.B Implement Micro-Partitioning.C Upgrade HMC to support P

题目
单选题
A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()
A

Upgrade OS to AIX 5.2.

B

Implement Micro-Partitioning.

C

Upgrade HMC to support POWER5.

D

Install Partition Load Manager.


相似考题
更多“单选题A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()A Upgrade OS to AIX 5.2.B Implement Micro-Partitioning.C Upgrade HMC to support P”相关问题
  • 第1题:

    Companycom has a system running AIX 5.2 and wants to upgrade to AIX 5.3. What method would provide the quickest recovery if the upgrade failed?()

    • A、Use alt_disk_install
    • B、Backup image to NIM server
    • C、Backup using mksysb to DVD-RAM
    • D、Apply the upgrade and do not commit

    正确答案:A

  • 第2题:

    A customer wishes to replace 12 older small UNIX systems.  They are running out of floor space in their data center and any solution must take this into consideration.  Assuming that the applications are supported on all AIX versions, which of the following would best meet the customer’s requirements?()

    • A、A p650 running AIX v5.3
    • B、A p5-550 running AIX v5.3
    • C、A p5-570 running Advanced POWER Virtualization
    • D、Multiple rack-mounted p615s running dynamic LPAR

    正确答案:C

  • 第3题:

    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()

    • A、IBM Techline
    • B、IBM Supportline
    • C、IBM Software Distribution
    • D、IBM Hardware Support

    正确答案:B

  • 第4题:

    Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()

    • A、Upgrade the p690 to a p5 590 server running AIX 5.3
    • B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization
    • C、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters
    • D、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

    正确答案:D

  • 第5题:

    A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()

    • A、Upgrade system firmware to latest level
    • B、Upgrade to AIX 5.3
    • C、Upgrade HMC to version 6.1
    • D、Convert rootvg filesystems to JFS2

    正确答案:B

  • 第6题:

    A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()

    • A、A desk, as it not rack mountable
    • B、Ethernet connections to the POWER5 systems
    • C、Serial connections to the POWER5 systems
    • D、USB connections for the keyboard and mouse

    正确答案:B

  • 第7题:

    单选题
    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()
    A

    Include a new HMC in the order to connect to the p5 595

    B

    Include a pair of new HMCs in the order to connect to the p5 595

    C

    Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities

    D

    Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A customer wishes to replace 12 older small UNIX systems.  They are running out of floor space in their data center and any solution must take this into consideration.  Assuming that the applications are supported on all AIX versions, which of the following would best meet the customer’s requirements?()
    A

    A p650 running AIX v5.3

    B

    A p5-550 running AIX v5.3

    C

    A p5-570 running Advanced POWER Virtualization

    D

    Multiple rack-mounted p615s running dynamic LPAR


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    Companycom has a system running AIX 5.2 and wants to upgrade to AIX 5.3. What method would provide the quickest recovery if the upgrade failed?()
    A

    Use alt_disk_install

    B

    Backup image to NIM server

    C

    Backup using mksysb to DVD-RAM

    D

    Apply the upgrade and do not commit


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    You are helping the customer customer configure anthentication,a new asyncOS upgradebecomes available,what should you do?()
    A

    avoid mentioning the upgrade to the customer

    B

    schedule a convenient time to upgrade again, backing up the configuration before and after theupgrade

    C

    contact customer support and ask them to run the upgrade for you

    D

    immediately show the customer how to run the CLI command upgrade


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()
    A

    Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570

    B

    Designed a p670 because it supports AIX 5.1 partitions

    C

    Initially designed a solution supporting AIX 5.1 partitions

    D

    Gained customer approval for the final design prior to ordering the system


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has several small AIX applications that are expected to grow over the next several years.  The biggest challenge facing the customer is determining the growth rate of the applications and the I/T requirements needed to support the growth.  They are also concerned about the under-utilization of their IT resources.  What should the pSeries technical specialist recommend to address this challenge?()
    A

    Install a p615 per application.

    B

    Install a p650 with AIX 5.2 and dynamic LPAR and CUoD.

    C

    Install the appropriate solution once the requirements are understood.

    D

    Install a POWER5 system with AIX 5.3, Advanced POWER Virtualization, and CoD.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

    • A、What are the plans for Disaster Recovery? 
    • B、What are the plans for data migration? 
    • C、Would iSCSI meet your needs? 
    • D、How much space is available in the current storage systems?

    正确答案:B

  • 第14题:

    A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

    • A、p5 hardware, AIX 5.2, Virtual I/O Server
    • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
    • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
    • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

    正确答案:C

  • 第15题:

    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()

    • A、Include a new HMC in the order to connect to the p5 595
    • B、Include a pair of new HMCs in the order to connect to the p5 595
    • C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities
    • D、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

    正确答案:B

  • 第16题:

    Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()

    • A、Verify the ISV application runs on AIX 5.2
    • B、Power4 to POWER5 upgrades are not supported without a application recompile
    • C、Check the placement and size of the boot logical volume and disk space requirements on the S85
    • D、AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked

    正确答案:A

  • 第17题:

    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()

    • A、Order a new HMC to support the p5 system.
    • B、Attach the new p5 system to the existing HMC.
    • C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
    • D、Do nothing.  This system does not require an HMC.

    正确答案:A

  • 第18题:

    A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers.  The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server.  How can the specialist help the customer?()

    • A、Explain to the customer that they need an additional HMC for the POWER5 system.
    • B、Obtain a PO from the customer to purchase additional serial connections to the HMC.
    • C、Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.
    • D、Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.

    正确答案:A

  • 第19题:

    单选题
    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()
    A

    IBM Techline

    B

    IBM Supportline

    C

    IBM Software Distribution

    D

    IBM Hardware Support


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers.  The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server.  How can the specialist help the customer?()
    A

    Explain to the customer that they need an additional HMC for the POWER5 system.

    B

    Obtain a PO from the customer to purchase additional serial connections to the HMC.

    C

    Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.

    D

    Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()
    A

     PowerVM Lx86

    B

     PowerVM Express Edition

    C

     PowerVM Standard Edition

    D

     PowerVM Enterprise Edition


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()
    A

    Order a new HMC to support the p5 system.

    B

    Attach the new p5 system to the existing HMC.

    C

    Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.

    D

    Do nothing.  This system does not require an HMC.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()
    A

    Upgrade OS to AIX 5.2.

    B

    Implement Micro-Partitioning.

    C

    Upgrade HMC to support POWER5.

    D

    Install Partition Load Manager.


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()
    A

    A desk, as it not rack mountable

    B

    Ethernet connections to the POWER5 systems

    C

    Serial connections to the POWER5 systems

    D

    USB connections for the keyboard and mouse


    正确答案: A
    解析: 暂无解析