Update Siebel to include the study results.
Review the study results and LPAR worksheet with the customer.
Design detailed system configurations around the study results.
Work with the client executive and the brand manager to establish discounts.
第1题:
A sales specialist is presented with a very large, complex opportunity. The customer is in the process of identifying business requirements. Which of the following tasks is most important to position IBM as the leader to capture this opportunity?()
第2题:
A financial industry customer will consolidate their Intel-based servers to a p5-550 running AIX, and needs experienced technical services. What information should the account executive provide to the customer to assure them that the technical specialist has the required experience?()
第3题:
A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them. Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()
第4题:
The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors. The system is a test system to run AIX 5.2. The customer has stated a preference for internal disks for the boot devices. The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()
第5题:
The account team is putting together a very complex solution for the customer. During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified. What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
第6题:
Would 10/100 Ethernets work as well?
Should there be eight fibre channel adapters?
Should there be an async adapter for heartbeat?
Will all LPARs need access to a common fibre channel tape drive?
第7题:
The technical support specialist has completed a UNIX course at college.
The technical specialist has supported several similar projects and has earned an IBM AIX certification.
The technical support specialist’s company sells $3M of UNIX computer systems every year.
The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.
第8题:
The technical specialist has supported multiple Cluster 1350 environments. References will be provided.
The technical specialist is Linux-certified by two industry groups. Certificate copies will be provided.
The technical specialist has worked on multiple UNIX consolidation projects. References will be provided.
The technical specialist has worked on Linux consolidation efforts. References will be provided.
第9题:
Use eConfig to configure and validate each pSeries and p5 system.
Engage Advanced Technical Support to review any outstanding technical issues.
Confirm with the customer that the solution design meets their requirements.
Perform a Pre-Install Solution Assurance Review to validate required power requirements.
第10题:
LVT
eSAR
eConfig
PCRS6000
第11题:
Update Siebel to include the study results.
Review the study results and LPAR worksheet with the customer.
Design detailed system configurations around the study results.
Work with the client executive and the brand manager to establish discounts.
第12题:
It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.
It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.
It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.
It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.
第13题:
A customer has defined their server needs as a four-LPAR 16-way p570 with 64GB of memory, four 10/100/1000 TX LAN adapters, and six fibre channel adapters to external storage in an IBM ESS (Shark). They like the idea of being able to do SAN maintenance while not incurring downtime. If all LPARs are production related and similar, which question is most appropriate for the pSeries technical specialist to ask?()
第14题:
The database on a p5-570 Micro-Partition has grown and backups are not meeting the Service Level Agreement. There are several partitions using the Virtual I/O Server to access the storage array. The database backup has high CPU utilization while the others have low CPU utilization. What adjustment can the technical specialist make to ensure that the Service Level Agreement is achieved?()
第15题:
Company.com has a single pSeries server with two shared processor logical partitions. The first partition has peak resource requirements during weekdays. The second partition has peak resource requirements during weekends. During the peak times, the total workload between the partitions does NOT exceed the capacity of the server. However, the partitions are not able to utilize the full capacity of the system during peak times, because the necessary CPU and memory resources are not always allocated to the busiest partition. Which of the following options would best balance these resources?()
第16题:
A pSeries technical specialist has completed a server consolidation study of a customer’s environment. An LPAR worksheet was produced, which details the resource (CPU, memory, disk, adapters) requirements for each OS image (partition) based on workload. What is the most appropriate next step?()
第17题:
Design the solution and present it confidently so the customer does not question it.
Design the solution and ensure the customer understands the unknowns with the new technology.
Explain to the customer that the VIO Server does not benefit them when doing server consolidation so it has not been configured.
Explain to the customer that the details surrounding the VIO Server have not been clearly defined so designing a solution is premature.
第18题:
Create LVM mirrors between LUNs
MPIO is necessary as the device driver
Use separate fibre adapters in the Virtual IO Server for each LUN
Virtual IO Server is a disk subsystem and must control the LUNs behind it
第19题:
A
B
C
D
第20题:
Some Express Configurations limit the amount of maximum memory at order time.
The customer must meet minimum system requirements to obtain Express Configuration pricing.
The Express Configurations offer less than the maximum number of processors.
The Express Configurations are only offered through the QuickShip Program.
第21题:
Add memory to the database partition to improve response time.
Add additional Host Bus Adapters to the server to improve IO throughput.
Modify CPU allocations to favor the database partition.
Increase CPU allocations to the Virtual I/O Server.
第22题:
Call the IBM Client Representative and ask the rep to influence the company’s executives.
Develop a strategy to better understand and possibly influence the customer’s success criteria.
Using IBM’s opportunity management system, request a technical team be formed to design a solution.
Nominate the customer for a funded IBM Server Consolidation study.
第23题:
Configure AIX Workload Manager
Configure Partition Load Manager
Configure eServer Workload Manager
Use DLPAR from the HMC
第24题:
Customer Engineer
Storage Sales Specialist
Competeline Representative
Field Technical Storage Specialist (pre-sales)