单选题A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following

题目
单选题
A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()
A

Have optional Fibre Channel and Ethernet switches been installed in the server?

B

What is the available kVA value of the UPS?

C

Are there sufficient empty socket outlets in the UPS?

D

What is the impact on the power consumption of the data center cooling system?


相似考题
参考答案和解析
正确答案: C
解析: 暂无解析
更多“单选题A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following”相关问题
  • 第1题:

    Which of the following is the MOST important physical consideration when deploying a new server?()

    • A、Humidity monitors, Biometrics, and fire suppression
    • B、Cooling, rack space, and power requirements
    • C、Service level agreements, uninterruptible power supply (UPS) deployment, and CCTV
    • D、Biometrics, fire suppression, and power requirements

    正确答案:B

  • 第2题:

    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()

    • A、Have the PDU requirements been met?
    • B、Are there sufficient KVM connections?
    • C、Is there sufficient service clearance?
    • D、Is there sufficient space in the existing rack?

    正确答案:A

  • 第3题:

    A Dell customer decided to use IBM Director and xSeries to manage their servers.  They purchased 10 IBM x336 servers and they already have 75 various Dell servers.  Which TWO steps need to be verified to be able to manage the mixed environment with IBM Director?()

    • A、Verify that the Dell systems have TCP/IP enabled
    • B、Verify that the systems are running the IBM Director Agent
    • C、Verify that the managed systems are SMBIOS 2.1 and WfM 2.0 compliant
    • D、Verify that the Dell systems have at least a 1GB of memory installed
    • E、Install an SNMP agent on the Dell systems as IBM Director cannot manage Industry Standard non-IBM servers

    正确答案:B,C

  • 第4题:

    A customer has requested five rack mounted servers, and a rack. They want redundant power connections. Which of the following is required to meet these requirements?()

    • A、Redundant power supplies on the servers
    • B、Redundant PDUs in the rack
    • C、edundant power supplies in the servers and redundant PDUs in the rack
    • D、Redundant power supplies in the servers, redundant PDUs in the rack, and Active Energy Manager (AEM)

    正确答案:C

  • 第5题:

    A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path.  From the following options, which is the preferred migration path?()

    • A、Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.
    • B、Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.
    • C、Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.
    • D、Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.

    正确答案:C

  • 第6题:

    单选题
    A customer has requested five rack mounted servers, and a rack. They want redundant power connections. Which of the following is required to meet these requirements?()
    A

    Redundant power supplies on the servers

    B

    Redundant PDUs in the rack

    C

    edundant power supplies in the servers and redundant PDUs in the rack

    D

    Redundant power supplies in the servers, redundant PDUs in the rack, and Active Energy Manager (AEM)


    正确答案: C
    解析: 暂无解析

  • 第7题:

    单选题
    Which of the following is the MOST important physical consideration when deploying a new server?()
    A

     Humidity monitors, Biometrics, and fire suppression

    B

     Cooling, rack space, and power requirements冷

    C

     Service level agreements, uninterruptible power supply (UPS) deployment, and CCTV

    D

     Biometrics, fire suppression, and power requirements


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    An administrator has a single 14U rack.  The administrator needs to install fifteen servers; rack-mounted redundant uninterruptible power supplies (UPSs), a network switch, and a KVM.  Which of the following server types would be BEST suited for this scenario?()
    A

    Blade servers

    B

    Rackmount servers

    C

    Tower servers

    D

    Web servers


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
    A

    Have the PDU requirements been met?

    B

    Are there sufficient KVM connections?

    C

    Is there sufficient service clearance?

    D

    Is there sufficient space in the existing rack?


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    A customer is considering an Intel processor-based blade solution from a competitor. The customer is willing to share only the information that the competitor offers 96 Xeon processors per rack.  Which of the following IBM BladeCenter E benefits should the Sales Specialist emphasize first?()
    A

    Redundant Blowers

    B

    Availability of AMD and Intel Processors

    C

    Processor density

    D

    Advanced Management Module


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    Which IBM storage products allows for 960 TB (raw) in one standard IBM rack of the following?()
    A

    XIV system

    B

    DS5300

    C

    DS8800

    D

    Storwize V7000


    正确答案: A
    解析: 暂无解析

  • 第12题:

    多选题
    A customer is planning to implement a new x445 in their datacenter.Which TWO of the following should the customer prepare prior to the implementation to ensure a trouble free installation?()
    A

    Install the exhaust fan on top of the IBM NetBAY 42 Enterprise rack for extra cooling

    B

    Ensure a 260V power source for the x445 and BladeCenter is available for fully redundant power

    C

    Ensure a 220v power source for the x445 is available for fully redundant power

    D

    Install the new 10GBit Ethernet network to take advantage of the new network switch in the x445.

    E

    Have their Network Operation Staff review and assist connecting the new server to their existing network.


    正确答案: A,C
    解析: 暂无解析

  • 第13题:

    A customer is interested in reducing energy consumption and infrastructure consolidation for space. The customer needs a maximum of 14 servers in 7U rack.  Which IBM BladeCenter Chassis should be recommended? ()

    • A、BladeCenter E
    • B、BladeCenter H
    • C、BladeCenter T
    • D、BladeCenter HT

    正确答案:A

  • 第14题:

    A customer is considering an Intel processor-based blade solution from a competitor. The customer is willing to share only the information that the competitor offers 96 Xeon processors per rack.  Which of the following IBM BladeCenter E benefits should the Sales Specialist emphasize first?()

    • A、Redundant Blowers
    • B、Availability of AMD and Intel Processors
    • C、Processor density
    • D、Advanced Management Module

    正确答案:C

  • 第15题:

    A customer is looking for a new file and print server and is considering a 2-socket Intel server with redundant power and hard disk that must fit in the current server rack. With 2U available in the rack, the customer is looking for the best price performance ratio.  Which IBM server will fit the best for this customer?()

    • A、x3200
    • B、x3455
    • C、x3550
    • D、x3650

    正确答案:C

  • 第16题:

    A customer is searching for a new, small business server. The customer is standardized on AMD and does not want to place the new server in a rack.  Which IBM server will best fit this customers requirement? ()

    • A、x3105
    • B、x3200
    • C、x3400
    • D、x3455

    正确答案:A

  • 第17题:

    A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()

    • A、Have optional Fibre Channel and Ethernet switches been installed in the server?
    • B、What is the available kVA value of the UPS?
    • C、Are there sufficient empty socket outlets in the UPS?
    • D、What is the impact on the power consumption of the data center cooling system?

    正确答案:B

  • 第18题:

    单选题
    A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()
    A

    Have optional Fibre Channel and Ethernet switches been installed in the server?

    B

    What is the available kVA value of the UPS?

    C

    Are there sufficient empty socket outlets in the UPS?

    D

    What is the impact on the power consumption of the data center cooling system?


    正确答案: A
    解析: 暂无解析

  • 第19题:

    单选题
    A customer is interested in reducing energy consumption and infrastructure consolidation for space. The customer needs a maximum of 14 servers in 7U rack.  Which IBM BladeCenter Chassis should be recommended? ()
    A

    BladeCenter E

    B

    BladeCenter H

    C

    BladeCenter T

    D

    BladeCenter HT


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer is searching for a new, small business server. The customer is standardized on AMD and does not want to place the new server in a rack.  Which IBM server will best fit this customers requirement? ()
    A

    x3105

    B

    x3200

    C

    x3400

    D

    x3455


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer is looking for a new file and print server and is considering a 2-socket Intel server with redundant power and hard disk that must fit in the current server rack. With 2U available in the rack, the customer is looking for the best price performance ratio.  Which IBM server will fit the best for this customer?()
    A

    x3200

    B

    x3455

    C

    x3550

    D

    x3650


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A medical customer has a rack with four BladeCenter H chassis that have been operating normally for several months. After installing a new rack of servers in the data center, the system administrator notices the blowers in the BladeCenters have increased their speed. Which of the following caused this problem? ()
    A

    The room temperature has reached 23C (73.4F). 

    B

    A Blade within the chassis has been shut down. 

    C

    The ambient temperature in the data center has increased 

    D

    One of the additional System X servers in the BladeCenter rack has failed.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path.  From the following options, which is the preferred migration path?()
    A

    Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.

    B

    Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.

    C

    Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.

    D

    Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.


    正确答案: D
    解析: 暂无解析

  • 第24题:

    单选题
    Which of the following is the MOST important physical consideration when deploying a new server?()
    A

    Humidity monitors, Biometrics, and fire suppression

    B

    Cooling, rack space, and power requirements

    C

    Service level agreements, uninterruptible power supply (UPS) deployment, and CCTV

    D

    Biometrics, fire suppression, and power requirements


    正确答案: B
    解析: 暂无解析