单选题Following an unscheduled power outage, theadministrator needs to power up an IVM-managed system. For the given system,what is the first step in this process?()A Physically press the appropriate button on the system.B Physically disconnect and reconnect

题目
单选题
Following an unscheduled power outage, theadministrator needs to power up an IVM-managed system. For the given system,what is the first step in this process?()
A

Physically press the appropriate button on the system.

B

Physically disconnect and reconnect the power cable on the system.

C

Log into the IVM using a Web Browser, select the managed-system and select the Power on option from the Operations menu.

D

Log into the HMC using a Web Browser, select the managed-system and select the Power on option from the Operations menu.


相似考题
更多“Following an unscheduled power outage, theadministrator need”相关问题
  • 第1题:

    You need to configure the power settings of your portable computer so that the display turns off when it is inactive and running on battery power. You also need to ensure that the power settings of the hard disk remain unaffected.What should you do?()

    A.A

    B.B

    C.C

    D.D


    参考答案:A

  • 第2题:

    An administrator notes that after a recent power outage, some open files were corrupted on one affected file server. Which of the following items should the administrator consider to determine the cause of this corruption?()

    • A、The server's memory
    • B、The server's RAID controller battery
    • C、The server's processor
    • D、The server's NIC teaming configuration

    正确答案:B

  • 第3题:

    Which of the following is MOST likely to occur if the temperature in the server room is cooled too quickly after a power outage?()

    • A、Server forms condensation
    • B、Server will not POST
    • C、Server’s services will not start
    • D、Server response times are slow due to temperature change

    正确答案:A

  • 第4题:

    An administrator notes that after a recent power outage, some open files were corrupted on oneaffected file server. Which of the following items should the administrator consider to determine the cause of this corruption?()

    • A、 The servers memory
    • B、 The servers RAID controller battery
    • C、 The servers processor
    • D、 The servers NIC teaming configuration

    正确答案:B

  • 第5题:

    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored?()

    • A、Identify which systems are the most critical and bring them up by level of importance.
    • B、Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
    • C、Identify the least critical systems and then power those systems on first.
    • D、Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

    正确答案:A

  • 第6题:

    Which of the following can occur if the maximum rated load is exceeded on an uninterruptible power supply (UPS)?()

    • A、 There is a fire hazard potential if a power outage occurs.
    • B、 The last system plugged into the UPS will not be provided any power.
    • C、 The UPS will draw more power from the circuit to compensate.
    • D、 The runtime of the UPS will be insufficient if a power outage occurs.

    正确答案:D

  • 第7题:

    Following an unscheduled power outage, theadministrator needs to power up an IVM-managed system. For the given system,what is the first step in this process?()

    • A、Physically press the appropriate button on the system.
    • B、Physically disconnect and reconnect the power cable on the system.
    • C、Log into the IVM using a Web Browser, select the managed-system and select the Power on option from the Operations menu.
    • D、Log into the HMC using a Web Browser, select the managed-system and select the Power on option from the Operations menu.

    正确答案:A

  • 第8题:

    Company.com recently experienced an unanticipated system outage when the VIO server was upgraded. The current p5-570 has six Micro-Partitions and a VIO server partition. How can a similar outage be avoided in the future?()

    • A、Use DLPAR to avoid an outage.
    • B、Deploy a redundant VIO server in the POWER5 system.
    • C、Add additional Host Bus Adapters and Network adapters to the VIO server.
    • D、Implement a standby server and move all partitions to it before applying future updates.

    正确答案:B

  • 第9题:

    A recent power outage disrupted customer operations in one of the two campus centers. Thecustomer has already started to develop a strategy for consolidation of the data centers andremote backup at a colocation facility, but current and near-term budgets are focused only oncapacity growth at lowest cost. Which of the following capabilities might be immediately attractiveto the customer?()

    • A、 DS8700 with remote mirroring 
    • B、 V7000 with Easy Tier and SSD 
    • C、 SVC VDisk mirroring with stretch clusters 
    • D、 UPS power backup to the racks with current storage controllers

    正确答案:C

  • 第10题:

    单选题
    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()
    A

     Identify which systems are the most critical and bring them up by level of importance.

    B

     Retrieve the latest backup tapes for immediate system restore using the GFS rotation.

    C

     Identify the least critical systems and then power those systems on first.

    D

     Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A recent power outage disrupted customer operations in one of the two campus centers. Thecustomer has already started to develop a strategy for consolidation of the data centers andremote backup at a colocation facility, but current and near-term budgets are focused only oncapacity growth at lowest cost. Which of the following capabilities might be immediately attractiveto the customer?()
    A

     DS8700 with remote mirroring 

    B

     V7000 with Easy Tier and SSD 

    C

     SVC VDisk mirroring with stretch clusters 

    D

     UPS power backup to the racks with current storage controllers


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    Which of the following can occur if the maximum rated load is exceeded on an uninterruptible power supply (UPS)?()
    A

    There is a fire hazard potential if a power outage occurs.

    B

    The last system plugged into the UPS will not be provided any power.

    C

    The UPS will draw more power from the circuit to compensate.

    D

    The runtime of the UPS will be insufficient if a power outage occurs.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A vessel proceeding to London,England,from New York makes an unscheduled call at the port of Hamilton,Bermuda.What term is used to denote the voluntary departure from the usual course?

    A.Alteration

    B.Deviation

    C.Liberty

    D.Unscheduled stop


    正确答案:B

  • 第14题:

    The system administrator did a new install of AIX on a server about a week ago. The system was not rebooted after the installation. CDE is running on this system as is TCPIP. The system administrator has started configuring the system percompany directives. The power cable was inadvertently disconnected from the wall causing the sever to lose power. Upon reboot, the system appears to hang during log in from the console or from Xterminals. Which of the following is the most probable cause?()

    • A、It is a hardware problem caused by the power failure.
    • B、There is a network problem, most probably with name resolution.
    • C、Sine the system was never rebooted, devices are marked defined instead of available and need to be activated.
    • D、Some filesets may be marked as broken and need to be reinstalled.

    正确答案:B

  • 第15题:

    Which of the following information would be on a system classification list?()

    • A、Disk drive size
    • B、IP address
    • C、Acceptable outage time
    • D、Operating system version

    正确答案:C

  • 第16题:

    Which of the following tools can be used to identify the location of a network outage?()

    • A、traceroute
    • B、netstat
    • C、nslookup
    • D、ping

    正确答案:A

  • 第17题:

    There is a power outage and all servers are shut down properly by the uninterruptible power supply(UPS) software. When one of the servers starts up it displays a logical drive failed error. This server has two processors,16GB of memory, and a RAID 5 array with 10 drives.  Which of the following is the MOST likely cause?()

    • A、 A failed RAID controller
    • B、 Two failed processors
    • C、 Two failed sticks of memory
    • D、 Two failed drives

    正确答案:D

  • 第18题:

    A user states that whenever they try to launch a certain installed application, they hear unusual whirring/clicking sounds from their machine and the application never loads. Which of the following components would a technician MOST likely need to replace?()

    • A、Hard Disk Drive
    • B、Optical Drive
    • C、Power Supply Unit
    • D、Case Fan

    正确答案:A

  • 第19题:

    Which of the following is a situation where dual (redundant) HMCs are recommended()? 

    • A、When managing more than four VIO servers.
    • B、When installed with Power 570 and larger hardware.
    • C、When hosting both Linux and AIX on the same physical hardware.
    • D、When unexpected outage on a single HMC would prove an untenable risk for the hosted LPARs.

    正确答案:D

  • 第20题:

    Company.com is ordering a new p5-570 and planning for the option of using Capacity on  Demand to activate additional resources in the future. Which of the following is a prerequisite to support the addition of CPUs or memory without an outage?()

    • A、Use Micro-Partitioning
    • B、Configure a Virtual I/O Server
    • C、Configure dynamic logical partitions
    • D、Activate Advanced POWER Virtualization

    正确答案:C

  • 第21题:

    You need to configure the power settings of your portable computer so that the display turns off when it is inactive and running on battery power. You also need to ensure that the power settings of the hard disk remain unaffected.  What should you do?()

    • A、Change the advanced power settings of the Balanced power plan.
    • B、Configure the portable computer to use the Power saver power plan.
    • C、Configure the portable computer to use the High performance power plan.
    • D、Restore the Power Saver power plan to the default settings.

    正确答案:A

  • 第22题:

    单选题
    Which of the following information would be on a system classification list? ()
    A

     Disk drive size

    B

     IP address

    C

     Acceptable outage time

    D

     Operating system version


    正确答案: A
    解析: 暂无解析

  • 第23题:

    多选题
    Which of the following are attributes of a hardware-based RAID controller?()
    A

    Backs up data

    B

    Less expensive than software RAID

    C

    Vendor neutral implementation

    D

    Accessible through a BIOS interface

    E

    More host CPU usage than software RAID

    F

    Accessible through a system utility after the OS has been loaded

    G

    May retain data in the event of a power outage


    正确答案: F,D
    解析: 暂无解析

  • 第24题:

    单选题
    An administrator notes that after a recent power outage, some open files were corrupted on oneaffected file server. Which of the following items should the administrator consider to determine the cause of this corruption?()
    A

     The servers memory

    B

     The servers RAID controller battery

    C

     The servers processor

    D

     The servers NIC teaming configuration


    正确答案: C
    解析: 暂无解析