单选题During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to on

题目
单选题
During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()
A

 None,everything can be done with the cluster active.

B

 Minimal downtime will be required to import the volume groups.

C

 Several hours are required for testing before final synchronization.

D

 Minimal downtime will be required to connect and test the serial network.


相似考题
参考答案和解析
正确答案: B
解析: 暂无解析