单选题A failure of the primary data center has occurred.  A warm site is available for use.  Which of the following should be done FIRST to bring the critical applications online?()A Run cabling and power to the warm site.B Restore data to the equipment.C Tr

题目
单选题
A failure of the primary data center has occurred.  A warm site is available for use.  Which of the following should be done FIRST to bring the critical applications online?()
A

Run cabling and power to the warm site.

B

Restore data to the equipment.

C

Transfer all data tapes over to the warm site.

D

Restore least critical applications online to test to make sure the site is functioning.


相似考题
参考答案和解析
正确答案: A
解析: 暂无解析
更多“单选题A failure of the primary data center has occurred.  A warm site is available for use.  Which of the following should be done FIRST to bring the critical applications online?()A Run cabling and power to the warm site.B Restore data to the equipment.C Tr”相关问题
  • 第1题:

    Which of the following disaster recovery sites requires power and cabling to be run before it can be used?()

    • A、 Hot site
    • B、 Cold site
    • C、 Warm site
    • D、 Failover site

    正确答案:B

  • 第2题:

    Which of the following should be done FIRST to a hard drive before it is disposed?()

    • A、Partition
    • B、Physical damage
    • C、Data wipe
    • D、Format

    正确答案:C

  • 第3题:

    Which of the following is the BEST sequence to bare metal restore a server?()

    • A、 Determine backups available, restore backups, and verify data.
    • B、 Restore applications, restore data, and verify data.
    • C、 Restore OS, restore system applications, and restore data.
    • D、 Contact end users of outage, restore backup data, and verify data.

    正确答案:C

  • 第4题:

    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()

    • A、 Identify which systems are the most critical and bring them up by level of importance.
    • B、 Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
    • C、 Identify the least critical systems and then power those systems on first.
    • D、 Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

    正确答案:A

  • 第5题:

    An administrator needs to recover an HMC due to a failed disk. The disk has been replaced, allowing the administrator to reinstall the HMC back to the required release of software. Backups of both the HMC Console Data and Upgrade Data are available. After reloading the HMC with the Recovery DVDs, what are the next steps to restore the HMC configuration?()

    • A、Use the 'HMC Management > Restore HMC Data' option to first restore just the HMC Data..
    • B、Use the 'HMC Management > Restore Upgrade Data' option to first restore just the Upgrade Data.
    • C、Use the 'HMC Management > Restore HMC Data' option to first restore the HMC Data and then the Upgrade Data.
    • D、Use the 'HMC Management > Restore Upgrade Data' option to first restore the Upgrade Data, and then the HMC Data.

    正确答案:A

  • 第6题:

    单选题
    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored?()
    A

    Identify which systems are the most critical and bring them up by level of importance.

    B

    Retrieve the latest backup tapes for immediate system restore using the GFS rotation.

    C

    Identify the least critical systems and then power those systems on first.

    D

    Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.


    正确答案: A
    解析: 暂无解析

  • 第7题:

    单选题
    An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.  Which of the following site types should be considered to meet these requirements? ()
    A

     Hot site

    B

     Warm site

    C

     Cold site

    D

     Active failover site


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    An administrator needs to recover an HMC due to a failed disk. The disk has been replaced, allowing the administrator to reinstall the HMC back to the required release of software. Backups of both the HMC Console Data and Upgrade Data are available. After reloading the HMC with the Recovery DVDs, what are the next steps to restore the HMC configuration?()
    A

    Use the 'HMC Management > Restore HMC Data' option to first restore just the HMC Data..

    B

    Use the 'HMC Management > Restore Upgrade Data' option to first restore just the Upgrade Data.

    C

    Use the 'HMC Management > Restore HMC Data' option to first restore the HMC Data and then the Upgrade Data.

    D

    Use the 'HMC Management > Restore Upgrade Data' option to first restore the Upgrade Data, and then the HMC Data.


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    Which of the following disaster recovery sites requires power and cabling to be run before it can be used?()
    A

     Hot site

    B

     Cold site

    C

     Warm site

    D

     Failover site


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    Which of the following is the BEST sequence to bare metal restore a server?()
    A

     Determine backups available, restore backups, and verify data.

    B

     Restore applications, restore data, and verify data.

    C

     Restore OS, restore system applications, and restore data.

    D

     Contact end users of outage, restore backup data, and verify data.


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    An administrator is attempting to recover from a power failure in the data center. Which of the following is the BEST way to recover the servers?()
    A

     Bring up the WINS server, the DNS server, then the web server

    B

     Bring up the web server, the time clock server, then the DHCP server

    C

     Bring up the backup tape server, the DNS server, then the web server

    D

     Bring up the active directory server, the DNS server, then the web server


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center. Which of the following site types should be considered to meet these requirements?()
    A

    Hot site

    B

    Warm site

    C

    Cold site

    D

    Active failover site


    正确答案: A
    解析: 暂无解析

  • 第13题:

    A failure of the primary data center has occurred.  A warm site is available for use.  Which of the following should be done FIRST to bring the critical applications online?()

    • A、Run cabling and power to the warm site.
    • B、Restore data to the equipment.
    • C、Transfer all data tapes over to the warm site.
    • D、Restore least critical applications online to test to make sure the site is functioning.

    正确答案:B

  • 第14题:

    An administrator is attempting to recover from a power failure in the data center. Which of the following is the BEST way to recover the servers?()

    • A、 Bring up the WINS server, the DNS server, then the web server
    • B、 Bring up the web server, the time clock server, then the DHCP server
    • C、 Bring up the backup tape server, the DNS server, then the web server
    • D、 Bring up the active directory server, the DNS server, then the web server

    正确答案:D

  • 第15题:

    An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.  Which of the following site types should be considered to meet these requirements? ()

    • A、 Hot site
    • B、 Warm site
    • C、 Cold site
    • D、 Active failover site

    正确答案:B

  • 第16题:

    An administrator has received complaints from users that an application is not available while other applications run. This application resides on an NFS mounted filesystem. Which of the following commands should be run as a reasonable first step to handle this problem?()

    • A、df
    • B、showmount
    • C、exportfs
    • D、refresh -g nfs

    正确答案:A

  • 第17题:

    A customer has one IBM System Storage DS8700 in their main data center with one DS6800 at a secondary site. They are using the Global Copy feature between the sites. They want to bring up a test image at the secondary site using the primary site data. Which sequence of actions will properly bring up the secondary site?()

    • A、bring up the secondary site on the target disks
    • B、suspend and bring up the secondary site on the target disks
    • C、perform a FlashCopy and bring up the secondary site on the target disks
    • D、"go-to-sync", perform aFlashCopy, and bring up the secondary site on the target disks

    正确答案:D

  • 第18题:

    单选题
    A customer has one IBM System Storage DS8700 in their main data center with one DS6800 at a secondary site. They are using the Global Copy feature between the sites. They want to bring up a test image at the secondary site using the primary site data. Which sequence of actions will properly bring up the secondary site?()
    A

    bring up the secondary site on the target disks

    B

    suspend and bring up the secondary site on the target disks

    C

    perform a FlashCopy and bring up the secondary site on the target disks

    D

    go-to-sync, perform aFlashCopy, and bring up the secondary site on the target disks


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    A customer needs the ability to recover their data if a total system failure occurs.  Which two of the following are the most important considerations in determining the solution?()
    A

    Network utilization

    B

    Total amount of storage installed

    C

    Amount of open files in the backup

    D

    Amount of critical data in the backup or restore


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    An administrator has received complaints from users that an application is not available while other applications run. This application resides on an NFS mounted filesystem. Which of the following commands should be run as a reasonable first step to handle this problem?()
    A

    df

    B

    showmount

    C

    exportfs

    D

    refresh -g nfs


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    Which of the following is the BEST sequence to bare metal restore a server?()
    A

    Determine backups available, restore backups, and verify data.

    B

    Restore applications, restore data, and verify data.

    C

    Restore OS, restore system applications, and restore data.

    D

    Contact end users of outage, restore backup data, and verify data.


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()
    A

     Identify which systems are the most critical and bring them up by level of importance.

    B

     Retrieve the latest backup tapes for immediate system restore using the GFS rotation.

    C

     Identify the least critical systems and then power those systems on first.

    D

     Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.


    正确答案: B
    解析: 暂无解析

  • 第23题:

    多选题
    Which three are benefits of A virtualized data center solution over A typical implementation?()
    A

    more efficient power consumption

    B

    fewer applications per server

    C

    less rack space

    D

    more efficient routing

    E

    more control over each server

    F

    simplified cabling


    正确答案: C,D
    解析: 暂无解析