Run cabling and power to the warm site.
Restore data to the equipment.
Transfer all data tapes over to the warm site.
Restore least critical applications online to test to make sure the site is functioning.
第1题:
Which of the following disaster recovery sites requires power and cabling to be run before it can be used?()
第2题:
Which of the following should be done FIRST to a hard drive before it is disposed?()
第3题:
Which of the following is the BEST sequence to bare metal restore a server?()
第4题:
A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()
第5题:
An administrator needs to recover an HMC due to a failed disk. The disk has been replaced, allowing the administrator to reinstall the HMC back to the required release of software. Backups of both the HMC Console Data and Upgrade Data are available. After reloading the HMC with the Recovery DVDs, what are the next steps to restore the HMC configuration?()
第6题:
Identify which systems are the most critical and bring them up by level of importance.
Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
Identify the least critical systems and then power those systems on first.
Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.
第7题:
Hot site
Warm site
Cold site
Active failover site
第8题:
Use the 'HMC Management > Restore HMC Data' option to first restore just the HMC Data..
Use the 'HMC Management > Restore Upgrade Data' option to first restore just the Upgrade Data.
Use the 'HMC Management > Restore HMC Data' option to first restore the HMC Data and then the Upgrade Data.
Use the 'HMC Management > Restore Upgrade Data' option to first restore the Upgrade Data, and then the HMC Data.
第9题:
Hot site
Cold site
Warm site
Failover site
第10题:
Determine backups available, restore backups, and verify data.
Restore applications, restore data, and verify data.
Restore OS, restore system applications, and restore data.
Contact end users of outage, restore backup data, and verify data.
第11题:
Bring up the WINS server, the DNS server, then the web server
Bring up the web server, the time clock server, then the DHCP server
Bring up the backup tape server, the DNS server, then the web server
Bring up the active directory server, the DNS server, then the web server
第12题:
Hot site
Warm site
Cold site
Active failover site
第13题:
A failure of the primary data center has occurred. A warm site is available for use. Which of the following should be done FIRST to bring the critical applications online?()
第14题:
An administrator is attempting to recover from a power failure in the data center. Which of the following is the BEST way to recover the servers?()
第15题:
An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center. Which of the following site types should be considered to meet these requirements? ()
第16题:
An administrator has received complaints from users that an application is not available while other applications run. This application resides on an NFS mounted filesystem. Which of the following commands should be run as a reasonable first step to handle this problem?()
第17题:
A customer has one IBM System Storage DS8700 in their main data center with one DS6800 at a secondary site. They are using the Global Copy feature between the sites. They want to bring up a test image at the secondary site using the primary site data. Which sequence of actions will properly bring up the secondary site?()
第18题:
bring up the secondary site on the target disks
suspend and bring up the secondary site on the target disks
perform a FlashCopy and bring up the secondary site on the target disks
go-to-sync, perform aFlashCopy, and bring up the secondary site on the target disks
第19题:
Network utilization
Total amount of storage installed
Amount of open files in the backup
Amount of critical data in the backup or restore
第20题:
df
showmount
exportfs
refresh -g nfs
第21题:
Determine backups available, restore backups, and verify data.
Restore applications, restore data, and verify data.
Restore OS, restore system applications, and restore data.
Contact end users of outage, restore backup data, and verify data.
第22题:
Identify which systems are the most critical and bring them up by level of importance.
Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
Identify the least critical systems and then power those systems on first.
Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.
第23题:
more efficient power consumption
fewer applications per server
less rack space
more efficient routing
more control over each server
simplified cabling