单选题Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()A Enable remote commands on the HMC Configuration menu,then use ssh to logi

题目
单选题
Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()
A

Enable remote commands on the HMC Configuration menu,then use ssh to login to theHMC,enter su - root

B

Login to the HMC as hscpe and run pesh,using a temporary password from IBM Support,afterward, enter su - root

C

Login to the HMC as hscroot,then run pesh,using a temporary password from IBM Support, afterward,enter su - root

D

Enable remote commands on the HMC Configuration menu,then telnet in as hscroot,entersu - root


相似考题
更多“单选题Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()A Enable remote commands on the HMC Configuration menu,then use ssh to logi”相关问题
  • 第1题:

    Which port must be open on the HMC to allow remote web access?() 

    • A、22
    • B、80
    • C、443
    • D、8080

    正确答案:C

  • 第2题:

    Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()

    • A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 
    • B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 
    • C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 
    • D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

    正确答案:B

  • 第3题:

    A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()

    • A、The routes on the HMC
    • B、The firewall setting of the LAN adapter
    • C、The name resolution protocol on the p5 590 server
    • D、The subnet mask settings on the Ethernet adapters

    正确答案:B

  • 第4题:

    On which HMC GUI panel can the ’Enable Electronic Service Agent’ option be found?() 

    • A、HMC Management
    • B、Systems Management
    • C、Service Management
    • D、Electronic Management

    正确答案:C

  • 第5题:

    Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()

    • A、Enable remote commands on the HMC Configuration menu,then use ssh to login to theHMC,enter su - root
    • B、Login to the HMC as hscpe and run pesh,using a temporary password from IBM Support,afterward, enter su - root
    • C、Login to the HMC as hscroot,then run pesh,using a temporary password from IBM Support, afterward,enter su - root
    • D、Enable remote commands on the HMC Configuration menu,then telnet in as hscroot,entersu - root

    正确答案:B

  • 第6题:

    A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?()

    • A、Enable automatic problem reporting from smit
    • B、Use IVM to enable console mirroring to IBM Remote Support.
    • C、Use the HMC to enable reporting through Electronic Service Agent.
    • D、Enable Automatic Problem Reporting in ASMI using he embedded modem on the FSP.

    正确答案:C

  • 第7题:

    单选题
    Which of the following procedures will allow an operator to access an LPAR console session?()
    A

    Open a vterm from the VIO graphical interface to get the partition console.

    B

    Open a vterm from the ASMI graphical interface to get the partition console.

    C

    Start an ssh session to the HMC. Use the vtmenu command to select the desired LPAR.

    D

    Start an ssh session to the VIO. Use the vtmenu command to select the desired LPAR.


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()
    A

    Implement a proxy server to provide multiple sources to one destination 

    B

    Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 

    C

    Purchase a network hub or switch so both p5 570s can connect to the single HMC 

    D

    Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    A pSeries technical specialist is performing a solutions assurance with a customer for a new single-frame 10-node p655 system being attached to a currently installed HMC.  Which of the following questions should be asked to gather all the required information to determine whether the p655 solution can connect to the HMC?()
    A

    Are there at least ten RS-232 ports available on the HMC?

    B

    Are there at least ten RS-422 ports available on the HMC?

    C

    Are there at least ten RS-232 and two RS-422 ports available on the HMC?

    D

    Are there at least two RS-232 and ten RS-422 ports available on the HMC?


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    The account executive is asking about post-sales support for a new p5 HMC.  They need the pSeries technical specialist to configure an HMC with software support for the customer.  Which of the following should the specialist include in the configuration?()
    A

    Supportline

    B

    ServiceSuite

    C

    Software Maintenance Agreement (SWMA)

    D

    Machine Control Program Remote Support Agreement (MCPRSA)


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()
    A

    The routes on the HMC

    B

    The firewall setting of the LAN adapter

    C

    The name resolution protocol on the p5 590 server

    D

    The subnet mask settings on the Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A system administrator wants to control the HMC from their workstation. Microsoft Windows 2000 is running and the HMC graphical user interface is being used remotely. Which of the following actions will accomplish this task?()
    A

    Use any Windows 2000 to graphically access the HMC

    B

    Load, install, and configure WebSM on the workstation

    C

    Telnet to the HMC using Exceed or a GUI emulator product from the workstation

    D

    Load, install, and configure OpenSSH or SSH on the workstation and access the HMC through the GUI interface


    正确答案: C
    解析: 暂无解析

  • 第13题:

    An administrator needs to recover an HMC due to a failed disk. The disk has been replaced, allowing the administrator to reinstall the HMC back to the required release of software. Backups of both the HMC Console Data and Upgrade Data are available. After reloading the HMC with the Recovery DVDs, what are the next steps to restore the HMC configuration?()

    • A、Use the 'HMC Management > Restore HMC Data' option to first restore just the HMC Data..
    • B、Use the 'HMC Management > Restore Upgrade Data' option to first restore just the Upgrade Data.
    • C、Use the 'HMC Management > Restore HMC Data' option to first restore the HMC Data and then the Upgrade Data.
    • D、Use the 'HMC Management > Restore Upgrade Data' option to first restore the Upgrade Data, and then the HMC Data.

    正确答案:A

  • 第14题:

    The account executive is asking about post-sales support for a new p5 HMC.  They need the pSeries technical specialist to configure an HMC with software support for the customer.  Which of the following should the specialist include in the configuration?()

    • A、Supportline
    • B、ServiceSuite
    • C、Software Maintenance Agreement (SWMA)
    • D、Machine Control Program Remote Support Agreement (MCPRSA)

    正确答案:D

  • 第15题:

    Which port must be open on the HMC to allow remoteweb access?()

    • A、22
    • B、80
    • C、443
    • D、8080

    正确答案:C

  • 第16题:

    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()

    • A、Implement a proxy server to provide multiple sources to one destination 
    • B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 
    • C、Purchase a network hub or switch so both p5 570s can connect to the single HMC 
    • D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

    正确答案:C

  • 第17题:

    A system administrator wants to control the HMC from their workstation. Microsoft Windows 2000 is running and the HMC graphical user interface is being used remotely. Which of the following actions will accomplish this task?()

    • A、Use any Windows 2000 to graphically access the HMC
    • B、Load, install, and configure WebSM on the workstation
    • C、Telnet to the HMC using Exceed or a GUI emulator product from the workstation
    • D、Load, install, and configure OpenSSH or SSH on the workstation and access the HMC through the GUI interface

    正确答案:B

  • 第18题:

    单选题
    Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()
    A

    Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 

    B

    The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 

    C

    If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 

    D

    The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
    A

    An 8-port adapter to the HMC

    B

    A hub for the private network

    C

    An additional Ethernet card to the HMC

    D

    An additional Ethernet card for each partition


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Which port must be open on the HMC to allow remote web access?()
    A

    22

    B

    80

    C

    443

    D

    8080


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()
    A

    Enable remote commands on the HMC Configuration menu,then use ssh to login to theHMC,enter su - root

    B

    Login to the HMC as hscpe and run pesh,using a temporary password from IBM Support,afterward, enter su - root

    C

    Login to the HMC as hscroot,then run pesh,using a temporary password from IBM Support, afterward,enter su - root

    D

    Enable remote commands on the HMC Configuration menu,then telnet in as hscroot,entersu - root


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()
    A

    An administrative VLAN with port 1808

    B

    Port 657 which must remain open to TCP/IP and UDP traffic

    C

    Network addresses are provided by DHCP services on the network

    D

    DHCP on the HMC is required to be on to communicate between LPAR and HMC


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch.  The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMc  

    B

    Asynchronous adapters on the new HMc

    C

    The two 570 servers are directly connected to the new HMc  

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    Which port must be open on the HMC to allow remoteweb access?()
    A

    22

    B

    80

    C

    443

    D

    8080


    正确答案: C
    解析: 暂无解析