单选题A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the p

题目
单选题
A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(1)处应选择()
A

phases

B

processes

C

segments

D

pieces


相似考题
参考答案和解析
正确答案: D
解析: 暂无解析
更多“A project life cycle is a collection of generally sequential”相关问题
  • 第1题:

    Typically, during which phase in a project life cycle are most of the project expenses incurred.

    A . Concept phase

    B . Development of design phase

    C . Execution phase.

    D . Termination phase.

    E . None of the above


    正确答案:C

  • 第2题:

    115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan

    B. a life cycle

    C. Development Plan

    D. a critical path

    E. Management Plan


    正确答案:B

  • 第3题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第4题:

    ● The sequential steps that define the process for successfully completing a project is:

    A Implementation Plan

    B a life cycle

    C Development Plan

    D a critical path

    E Management Plan


    正确答案:B

  • 第5题:

    ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

    A Conceptual

    B Development.

    C Execution

    D Finish

    E All of the above.


    正确答案:E

  • 第6题:

    ● The project life-cycle can be described as(72).

    (72)

    A.project concept, project planning, project execution, and project close-out

    B.project planning, work authorization, and project reporting

    C.project planning, project control, project definition, WBS development, and project termination

    D.project concept, project execution, and project reporting


    正确答案:A

    试题(72)分析
      关于项目周期划分正确的是  (72)  。
      A.启动、计划、执行、收尾
      B.计划、授权、报告
      C.计划、控制、方案设计、WBS的发展、终止
      D.启动、执行、报告
    参考答案
      (72)A

  • 第7题:

    根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces


    正确答案:A

  • 第8题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().

    A.development

    B.concept

    C.system analysis

    D.implementation


    正确答案:B

  • 第9题:

    A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.

    A. plan
    B. fraction
    C. main
    D.framework

    答案:D
    解析:
    一个项目的生命周期由若干个顺序相连的阶段组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的()

  • 第10题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第11题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施

  • 第12题:

    A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.

    A.phases
    B.processes
    C.segments
    D.pieces

    答案:A
    解析:
    一个项目的生命周期由若干个顺序相连的 () 组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。
    A.阶段B.过程C.片段D.碎片参考答案:A

  • 第13题:

    During which phase of the project life cycle is the amount at stake lowest?

    A concept

    B development

    C execution

    D conclusion

    E C and D


    正确答案:A

  • 第14题:

    167 The project life-cycle can be described as:

    A. project concept, project planning, project execution, and project close-out.

    B. project planning, work authorization, and project reporting.

    C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

    E. All of the above


    正确答案:A

  • 第15题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第16题:

    ● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A 5%

    B 10%

    C 15%

    D 25%

    E 50%


    正确答案:D

  • 第17题:

    ● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.

    (73)

    A. phases

    B. processes

    C. segments

    D. pieces

    (74)

    A. plan

    B. fraction

    C. main

    D. framework


    正确答案:A,D

  • 第18题:

    A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.

    A.phases

    B.processes

    C.segments

    D.pieces


    正确答案:A

  • 第19题:

    The (71) defines the phases that connect the beginning of a project to its end.

    A.milestone

    B.schedule

    C.temporary

    D.project life cycle


    正确答案:D

  • 第20题:

    A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
    The life cycle provides the basic for managing the project, regardless of the specific work involved.

    A.phases
    B.processes
    C.segments
    D. pieces

    答案:A
    解析:
    一个项目的生命周期由若干个顺序相连的(73)组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的。
    (73)A. 阶段 B. 过程 C. 片段 D. 碎片

  • 第21题:

    The project life-cycle can be described as().

    A.project concept, project planning, project execution, and project close-out
    B.project planning, work authorization, and project reporting
    C.project planning, project control, project definition, WBS development, and project termination
    D.project concept, project execution, and project reporting

    答案:A
    解析:
    关于项目周期划分正确的是(72)。

    A. 启动、计划、执行、收尾

    B. 计划、授权、报告

    C. 计划、控制、方案设计、WBS的发展、终止

    D. 启动、执行、报告

  • 第22题:

    There are four phases in the life cycle of a project:start,plan,execute and( ).

    A.implement
    B.performance
    C.end
    D.excute

    答案:C
    解析:
    项目的生命周期有四个阶段为启动、计划、执行与结束。A执行B执行C结束D执行

  • 第23题:

    The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:

  • 第24题:

    A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(2)处应选择()

    • A、plan
    • B、fraction
    • C、main
    • D、framework

    正确答案:D