第1题:
Typically, during which phase in a project life cycle are most of the project expenses incurred.
A . Concept phase
B . Development of design phase
C . Execution phase.
D . Termination phase.
E . None of the above
第2题:
115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan
B. a life cycle
C. Development Plan
D. a critical path
E. Management Plan
第3题:
185 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above
第4题:
● The sequential steps that define the process for successfully completing a project is:
A Implementation Plan
B a life cycle
C Development Plan
D a critical path
E Management Plan
第5题:
● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
第6题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第7题:
根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces
第8题:
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().
A.development
B.concept
C.system analysis
D.implementation
第9题:
第10题:
第11题:
第12题:
第13题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第14题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第15题:
67 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above.
第16题:
● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
第17题:
● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.
(73)
A. phases
B. processes
C. segments
D. pieces
(74)
A. plan
B. fraction
C. main
D. framework
第18题:
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
A.phases
B.processes
C.segments
D.pieces
第19题:
The (71) defines the phases that connect the beginning of a project to its end.
A.milestone
B.schedule
C.temporary
D.project life cycle
第20题:
第21题:
第22题:
第23题:
第24题:
A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(2)处应选择()