The()provides the project manager with the authority to apply organizational resources to project activities.
A

project management plan

B

contract

C

project human resource plan

D

project charter


相似考题
更多“The()provides the project manager with the authority to appl”相关问题
  • 第1题:

    A common way by which executives provide the project manager with written authority is through:

    A . A common job description for all project managers

    B . An appointment letter

    C . A project charter

    D . All of the above

    E . B and C only


    正确答案:E

  • 第2题:

    156 Expectancy theory as applied to project management implies that:

    A. The team will work the hardest on those goals that are clearly explained by the project manager

    B. The more rewards that the project manager provides, the better the performance of the team

    C. Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above


    正确答案:C

  • 第3题:

    182 The use of the project reports:

    A. are not necessary on small projects

    B. provides a means whereby various levels of authority can judge project performance

    C. provides insight into project areas and the effectiveness of the control systems

    D. All of the above

    E. B and C


    正确答案:E

  • 第4题:

    131 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

    A. Conflict in authority between project manager and functional managers

    B. Dual allegiance on part of team members

    C. Complex prioritization of resources

    D. Loss of developed procedures on project dissolution

    E. All of the above


    正确答案:E

  • 第5题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第6题:

    ● The project charter:

    A Expresses upper management commitment to the project.

    B Provides that authority by which the project will be run.

    C Establishes that organizational structure with the project.

    D Specifies overall objectives and timeframe. of the project.

    E All of the above.


    正确答案:E

  • 第7题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第8题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第9题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第10题:

    ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor anD.Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第11题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第12题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    projectcharter


    正确答案: D
    解析: 该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。

  • 第13题:

    Expectancy theory as applied to project management implies that:

    A The team will work the hardest on those goals that are clearly explained by the project manager

    B The more rewards that the project manager provides, the better the performance of the team

    C Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members

    E None of the above


    正确答案:C

  • 第14题:

    118 A common way by which executives provide the project manager with written authority is through:

    A. A common job description for all project managers

    B. An appointment letter

    C. A project charter

    D. All of the above

    E. B and C only


    正确答案:E

  • 第15题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第16题:

    13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

    A. Conflict in authority between project manager and functional managers

    B. Dual allegiance on part of team members "

    C. Complex prioritization of resources

    D. Loss of developed procedures on project dissolution

    E. All of the above


    正确答案:E

  • 第17题:

    ● The use of the project reports:

    A are not necessary on small projects

    B provides a means whereby various levels of authority can judge project performance

    C provides insight into project areas and the effectiveness of the control systems

    D All of the above

    E B and C


    正确答案:E

  • 第18题:

    ●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).

    (75) A. technical specifications

    B. performance specifications

    C. product descriptions

    D. quality assurance


    正确答案:A

  • 第19题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第20题:

    ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.

    (75) A. Resource assignment matrix

    B. Change control plan

    C. Project charter

    D. Client organization chart


    正确答案:B

  • 第21题:

    ( )is a process developing a document that formally authorizes the existence of a project and provides the
    project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor and Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第22题:

    Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.

    A.Resource assignment matrix
    B.Change control plan
    C.Project charter
    D.Client organization chart

    答案:B
    解析:
    在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,变更控制计划文件提供了该信息。 A.资源分配矩阵 B.变更控制计划 C.项目章程 D.客户组织结构图

  • 第23题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D