  • 第1题:

    ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

    (74) A. Product scope description

    B. Project objectives

    C. Product specification

    D. The project scope statement


    正确答案:D

  • 第2题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第3题:

    ● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.


    正确答案:B,D,A,C,D

  • 第4题:

    In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.

    A.schedule

    B.activity

    C.plan

    D.contractor@@@SXB@@@A.finding

    B.balance

    C.allocation

    D.distribution


    正确答案:A,C

  • 第5题:

    The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement
    B.project requirement
    C.project charter
    D.product specification

    答案:A
    解析:
    项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。
    A.项目范围说明书B.项目需求C.项目章程 D.产品规范

  • 第6题:

    In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。

    A.schedule
    B.activity
    C.Plan
    D.contractor

    答案:A
    解析:
    在项目管理中,( )是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。

  • 第7题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第8题:

    Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.

    A.independent resource
    B.individual work load
    C.work milestone
    D.work package

    答案:D
    解析:
    WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。A. 独立资源 B. 个人工作负荷C. 工作里程碑 D. 工作包

  • 第9题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第10题:

    单选题
    In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.
    A

    schedule

    B

    activity

    C

    plan

    D

    contractor


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.
    A

    Product scope description

    B

    Project objectives

    C

    Stakeholder Analysis

    D

    The project scope statement


    正确答案: A
    解析: 参考答案:D

  • 第12题:

    单选题
    The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
    A

    subdividing

    B

    assessing

    C

    planning

    D

    integrating


    正确答案: B
    解析: 该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)

  • 第13题:

    ● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

    (75)

    A.independent resource

    B.individual work load

    C.work milestone

    D.work package


    正确答案:D
    试题(75)分析
     WBS工作分解结构是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包work package的层次。
     独立资源independent resource、个人工作负荷individual work load以及工作里程碑work milestone都不是WBS分解的最小层级,因此选D。
    参考答案
    (75)D

  • 第14题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第15题:

    Operations( )is a document that describes in detail the processes。

    A.Paper

    B.Book

    C.Menu

    D.Manual


    正确答案:D

  • 第16题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第17题:

    ()describees,indetail,the project's deliverables and the work required to create those deliverables.


    A.Product scope description
    B.Project objectives
    C.Produce specification
    D.The project scope statement


    答案:D
    解析:
    项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。

  • 第18题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第19题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第20题:

    In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.

    • A、schedule
    • B、WBS
    • C、SOW
    • D、charter

    正确答案:A

  • 第21题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A

  • 第22题:

    单选题
    The()describes, in detail, the project's deliverables and the work required to create those deliverables.
    A

    project scope statement

    B

    project requirement

    C

    project charter

    D

    product specification


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
    A

    work performance information

    B

    scope statement

    C

    changerequests

    D

    process analysis


    正确答案: B
    解析: 该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。

  • 第24题:

    单选题
    Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
    A

    independentresource

    B

    individualworkload

    C

    workmilestone

    D

    workpackage


    正确答案: D
    解析: 暂无解析