单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A work performance informationB scope stat

题目
单选题
The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
A

work performance information

B

scope statement

C

changerequests

D

process analysis


相似考题
参考答案和解析
正确答案: B
解析: 该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。
更多“单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A work performance informationB scope stat”相关问题
  • 第1题:

    ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

    (74) A. Product scope description

    B. Project objectives

    C. Product specification

    D. The project scope statement


    正确答案:D

  • 第2题:

    ● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

    (72)

    A. Product scope description

    B. Project objectives

    C. Stakeholder Analysis

    D. The project scope statement


    正确答案:D

  • 第3题:

    The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B

  • 第4题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第5题:

    The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement
    B.project requirement
    C.project charter
    D.product specification

    答案:A
    解析:
    项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。
    A.项目范围说明书B.项目需求C.项目章程 D.产品规范

  • 第6题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第7题:

    ( )in not inc1uded in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告

  • 第8题:

    () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation

    答案:B
    解析:
    范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第9题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第10题:

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    • A、work performance information
    • B、scope statement
    • C、changerequests
    • D、process analysis

    正确答案:B

  • 第11题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A

  • 第12题:

    单选题
    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.
    A

    Product scope description

    B

    Project objectives

    C

    Stakeholder Analysis

    D

    The project scope statement


    正确答案: B
    解析: 参考答案:D

  • 第13题:

    is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.WBS Creation

    B.Scope definition

    C.Project acceptance

    D.Scope verification


    正确答案:D

  • 第14题:

    ( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

    A.Product scope description B.Project objectives C.Product specification D.The project scope statement


    正确答案:D

  • 第15题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第16题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第17题:

    ()describees,indetail,the project's deliverables and the work required to create those deliverables.


    A.Product scope description
    B.Project objectives
    C.Produce specification
    D.The project scope statement


    答案:D
    解析:
    项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。

  • 第18题:

    ( )is not included in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告。

  • 第19题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第20题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第21题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第22题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第23题:

    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、Project acceptance
    • B、Scope verification
    • C、Scope definition
    • D、WBS Creation

    正确答案:B

  • 第24题:

    单选题
    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
    A

    work performance information

    B

    scope statement

    C

    changerequests

    D

    process analysis


    正确答案: C
    解析: 该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。