单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future proje

题目
单选题
You are working on the cost budget for one project. Which of the following is true()
A

This process assigns cost estimates to project activities including risks and contingency plans.

B

The cost baseline will be used to measure variances and future project performance.

C

This process assigns cost estimates for expected future period operating costs.

D

The cost baseline is the expected cost for the project.


相似考题
更多“You are working on the cost budget for one project. Which of”相关问题
  • 第1题:

    You are working on the cost budget for one project. Which of the following is true()

    A.This process assigns cost estimates to project activities including risks and contingency plans.

    B.The cost baseline will be used to measure variances and future project performance.

    C.This process assigns cost estimates for expected future period operating costs.

    D.The cost baseline is the expected cost for the project.


    参考答案:B

  • 第2题:

    You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

    A.Ahead of schedule

    B.Behind schedule

    C.On schedule

    D.Having not enough information provided


    正确答案:B
    你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万工程款,完成了预算中28万的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____________。

  • 第3题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第4题:

    You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact.  In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()

    • A、loss of a tempfile
    • B、loss of a system data file
    • C、loss of one of the control files
    • D、loss of one of the tablespaces
    • E、loss of a member from each redo log group
    • F、loss of the only member of an unarchived redo log group

    正确答案:F

  • 第5题:

    You work in a company which uses SQL Server 2008. You are the administrator of the company database. Now you are in charge of a SQL Server 2008 instance. There are queries that have an estimated execution cost less than 3. You intend to configure the instance, make it use a single thread for these queries. In the options below, which sp_configure configuration option should you set?()

    • A、You should set query governor cost limit
    • B、You should set cost threshold for parallelism
    • C、You should set priority boost 
    • D、You should set precompute rank

    正确答案:B

  • 第6题:

    单选题
    Which one of the following repair will cost the least cost?()
    A

    Routine docking repair

    B

    Voyage repair

    C

    Damage repair

    D

    Conversion


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact. In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()
    A

     loss of one of the tablespaces

    B

     loss of a system data file

    C

     loss of one of the control files

    D

     loss of a tempfile

    E

     loss of the only member of an unarchived redo log group

    F

     loss of a member from each redo log group


    正确答案: E
    解析: 暂无解析

  • 第8题:

    ● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

    (74)

    A.Ahead of schedule

    B.Behind schedule

    C.On schedule

    D.Having not enough information provided


    正确答案:B

  • 第9题:

    Why are you working in a field other than the one in which you have a degree?


    正确答案:
              

  • 第10题:

    You are working on the cost budget for one project. Which of the following is true()

    • A、This process assigns cost estimates to project activities including risks and contingency plans.
    • B、The cost baseline will be used to measure variances and future project performance.
    • C、This process assigns cost estimates for expected future period operating costs.
    • D、The cost baseline is the expected cost for the project.

    正确答案:B

  • 第11题:

    In which two cases would you perform only consistent backup?()

    • A、You are working on a database where downtime is not tolerated.
    • B、You are working on a database where downtime can be tolerated.
    • C、You are working on a database that operates in ARCHIVELOG mode.
    • D、You are working on a database that operates in NOARCHIVELOG mode.
    • E、You are working on a database where all the tablespaces are locally managed.
    • F、You are working on a database where control files and redo log files are multiplexed.
    • G、You are working on a database where control files and redo log files are not multiplexed.

    正确答案:B,D

  • 第12题:

    单选题
    You are working on the cost budget for one project. Which of the following is true()
    A

    This process assigns cost estimates to project activities including risks and contingency plans.

    B

    The cost baseline will be used to measure variances and future project performance.

    C

    This process assigns cost estimates for expected future period operating costs.

    D

    The cost baseline is the expected cost for the project.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    单选题
    Wise buying is a positive way in which you can make your money go further. The ()you go about purchasing an article or a service can actually ()you money or can add ()the cost. Take the ()example of a hairdryer. If you are buying a hairdryer, you might ()that you are making the ()buy if you choose one ()look you like and which is also the cheapest ()price. But when you get it home you may find that it ()twice as long as a more expensive ()to dry your hair. The cost of the electricity plus the cost of your time could well ()your hairdryer the most expensive one of all. So what principles should you ()when you go out shopping? If you ()your home, your car or any valuable ()in excellent condition, you’ll be saving money in the long () Before you buy a new (),talk to someone who owns one. If you can, use it or borrow it to check it suits your particular () Before you buy an expensive (),or a service, do check the price and ()is on offer. If possible, choose ()three items or three estimates. 请在第()处填上正确答案。
    A

    function

    B

    purpose

    C

    goal

    D

    task


    正确答案: C
    解析: 暂无解析

  • 第14题:

    单选题
    You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact.  In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()
    A

    loss of a tempfile

    B

    loss of a system data file

    C

    loss of one of the control files

    D

    loss of one of the tablespaces

    E

    loss of a member from each redo log group

    F

    loss of the only member of an unarchived redo log group


    正确答案: E
    解析: 暂无解析