单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future proje

题目
单选题
You are working on the cost budget for one project. Which of the following is true()
A

This process assigns cost estimates to project activities including risks and contingency plans.

B

The cost baseline will be used to measure variances and future project performance.

C

This process assigns cost estimates for expected future period operating costs.

D

The cost baseline is the expected cost for the project.


相似考题
参考答案和解析
正确答案: A
解析: 暂无解析
更多“单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future proje”相关问题
  • 第1题:

    Which of the following is referred to as sunk cost:

    A . management reserve

    B . contingency fund

    C . cost budgeted for construction under water

    D . expended funds over which there is no further control

    E . forecasted budget over-runs


    正确答案:D

  • 第2题:

    Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A . Baseline costs

    B . Budgeted costs.

    C . Estimates upon completion costs

    D . Scheduled costs

    E . None of the above


    正确答案:A

  • 第3题:

    23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第4题:

    65 Which of the following is referred to as sunk cost:

    A. management reserve

    B. contingency fund

    C. cost budgeted for construction under water

    D. expended funds over which there is no further control

    E. forecasted budget over-runs


    正确答案:D

  • 第5题:

    114 The Cost Performance Index is computed as:

    A. budget cost of work performed divided by actual cost of work performed

    B. budget cost of work performed minus actual cost of work performed

    C. budget cost of work performed minus budget cost of work scheduled

    D. budget cost of work scheduled divided by budget cost of work performed

    E. actual cost of work scheduled divided by budget cost of work performed


    正确答案:A

  • 第6题:

    105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B. Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第7题:

    You are working on the cost budget for one project. Which of the following is true()

    A.This process assigns cost estimates to project activities including risks and contingency plans.

    B.The cost baseline will be used to measure variances and future project performance.

    C.This process assigns cost estimates for expected future period operating costs.

    D.The cost baseline is the expected cost for the project.


    参考答案:B

  • 第8题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第9题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第10题:

    Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.

    A.qulity
    B.risk
    C.change
    D.cost

    答案:D
    解析:
    本题翻译:
    挣值管理(EVM)将范围基线与()基线以及进度基线结合起来,形成绩效基线,帮助项目管理团队评估和衡量项目绩效和进度。
    A.质量B.风险C.变更D.成本
    其实此题只需要知道两个英文词就可以做出题,第一个就是EVM,挣值管理,属于成本管理里面用到的工具与技术,那此题答案就出来了,成本的英文就是D选项。所以英文题不需要会翻译所有的单词,记住题眼也是可以答题的,所以日常复习中,背几个英文单词,也很有帮助。
    题干多读几遍,有个印象,也是一个知识点。

  • 第11题:

    You are working on the cost budget for one project. Which of the following is true()

    • A、This process assigns cost estimates to project activities including risks and contingency plans.
    • B、The cost baseline will be used to measure variances and future project performance.
    • C、This process assigns cost estimates for expected future period operating costs.
    • D、The cost baseline is the expected cost for the project.

    正确答案:B

  • 第12题:

    单选题
    Which one of the following repair will cost the least cost?()
    A

    Routine docking repair

    B

    Voyage repair

    C

    Damage repair

    D

    Conversion


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Which of the following is considered a direct cost for producing a widget?

    A . The cost of the materials used to produce a widget.

    B . The labor costs of the workers who actually produced the widget.

    C . The rent for the building in which the widget was manufactured

    D . The salary of senior management and the project sponsor

    E . A and B only


    正确答案:E

  • 第14题:

    A Project Status Report would include all of the following except:

    A Cost and schedule reports

    B Changes to scope. cost or schedule

    C Narrative explanation of variances

    D Personnel problems on the project

    E Upcoming activities


    正确答案:D

  • 第15题:

    35 Which of the following is considered a direct cost for producing a widget?

    A. The cost of the materials used to produce a widget.

    B. The labor costs of the workers who actually produced the widget.

    C. The rent for the building in which the widget was manufactured

    D. The salary of senior management and the project sponsor

    E. A and B only


    正确答案:E

  • 第16题:

    84 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above.


    正确答案:B

  • 第17题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第18题:

    166 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above


    正确答案:B

  • 第19题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第20题:

    Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.

    A.accuracy

    B.approximation

    C.specification

    D.summary


    正确答案:B
    解析:估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本。成本估算包括识别和考虑各种成本计算方案。例如,在大多数的应用领域,普遍在设计阶段多做些额外工作以降低执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般以货币单位表示,以利于在项目内和项目间进行比较。项目范围说明书描述了项目的商业要求、理由、需求和当前边界。它提供了关于在成本估算时必须考虑的项目需求的重要信息。

  • 第21题:

    ( )is a process of monitoring the status of the project to update the project costs and manage changes is the cost baseline.

    A.Plan Cost Management
    B.Estimate Costs
    C.Determine Budget
    D.Control costs

    答案:B
    解析:
    控制成本是一个监控项目状态的过程,目的是更新项目成本并且对成本基准的变化进行管理。
    2019年11月软考(系统集成项目管理工程师)综合知识真题答案

    ◇2019年11月软考(系统集成项目管理工程师)综合知识真题答案
    若本套试卷含有主观题,针对主观题请自行参考解析评分
    单项选择题
    一、单项选择题(共75道题,每道题1.0分。)

  • 第22题:

    The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project.

    A. cost variance
    B.planneD.cost
    C.PlanneD.value
    D.actual cost

    答案:D
    解析:
    翻译:

    成本绩效指数是挣值和( )的比率,用来估算完成整个工程的预计费用。

    A. 成本差值 B. 计划成本 C. 计划值 D. 实际花费

  • 第23题:

    Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()

    • A、project scope statement
    • B、statement of work
    • C、project management plan
    • D、projectpolicy

    正确答案:A

  • 第24题:

    单选题
    You are working on the cost budget for one project. Which of the following is true()
    A

    This process assigns cost estimates to project activities including risks and contingency plans.

    B

    The cost baseline will be used to measure variances and future project performance.

    C

    This process assigns cost estimates for expected future period operating costs.

    D

    The cost baseline is the expected cost for the project.


    正确答案: B
    解析: 暂无解析