The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date r

题目

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

  • A、Data flow model
  • B、The project critical path
  • C、Resource loading chart
  • D、WBS (Work Breakdown Structure)

相似考题
更多“The project manager&”相关问题
  • 第1题:

    167 The project life-cycle can be described as:

    A. project concept, project planning, project execution, and project close-out.

    B. project planning, work authorization, and project reporting.

    C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

    E. All of the above


    正确答案:A

  • 第2题:

    139 The project charter is a document designed to tell _____ exactly what the project entails.

    A. The project manager

    B. The project office

    C. The project team

    D. The project sponsor

    E. Anyone associated with the project


    正确答案:E

  • 第3题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第4题:

    ● The project life-cycle can be described as(72).

    (72)

    A.project concept, project planning, project execution, and project close-out

    B.project planning, work authorization, and project reporting

    C.project planning, project control, project definition, WBS development, and project termination

    D.project concept, project execution, and project reporting


    正确答案:A

    试题(72)分析
      关于项目周期划分正确的是  (72)  。
      A.启动、计划、执行、收尾
      B.计划、授权、报告
      C.计划、控制、方案设计、WBS的发展、终止
      D.启动、执行、报告
    参考答案
      (72)A

  • 第5题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第6题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第7题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第8题:

    The project life-cycle can be described as().

    A.project concept, project planning, project execution, and project close-out
    B.project planning, work authorization, and project reporting
    C.project planning, project control, project definition, WBS development, and project termination
    D.project concept, project execution, and project reporting

    答案:A
    解析:
    关于项目周期划分正确的是(72)。

    A. 启动、计划、执行、收尾

    B. 计划、授权、报告

    C. 计划、控制、方案设计、WBS的发展、终止

    D. 启动、执行、报告

  • 第9题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第10题:

    () are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results.

    A.Controls
    B.Baselines
    C.Project stakeholders
    D.Project managers

    答案:C
    解析:
    项目干系人是积极参与到项目中,或其利益可能会受到项目执行或完成结果影响的个人或组织,他们可能会对项目及其结果施加影响。

  • 第11题:

    ( ) is primarily concerned with defining and controlling what is and is not included in the project.

    A.Project Time Management
    B.Project Cost Management
    C.Project Scope Management
    D.Project Communications Management

    答案:C
    解析:
    项目范围管理是项目管理(包括时间、成本、沟通)的基础。

    项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。

    选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理。因此应选择C。

  • 第12题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第13题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第14题:

    ● Interfacing with the customer after project go-ahead is the responsibility of:

    A Project sponsor

    B Project team

    C Project manager

    D Functional manager

    E All of the above are possible, based upon the size and complexity of the project


    正确答案:C

  • 第15题:

    ● (74) is primarily concerned with defining and controlling what is and is not included in the project.

    (74)

    A. Project Time Management

    B. Project Cost Management

    C. Project Scope management

    D. Project Communications Management


    正确答案:C

  • 第16题:

    are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

    A.Project manager

    B.Project team member

    C.Sponsor

    D.Proiect stakeholders


    正确答案:D
    解析:项目干系人是指那些积极参与项目或是其利益会受到项目执行或完成的结果影响的个人和组织。

  • 第17题:

    are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

    A.Controls

    B.Baselines

    C.Project stakeholders

    D.Project managers


    正确答案:C
    解析:项目干系人是积极参与到项目中,或其利益可能会受项目执行或完成结果影响的个人或组织:他们可能会对项目及其结果施加影响。

  • 第18题:

    Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

    A.Developing project charter

    B.Developing project management plan

    C.Analyzing project risks

    D.Monitoring and controlling project


    正确答案:C

  • 第19题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第20题:

    ( )is a process developing a document that formally authorizes the existence of a project and provides the
    project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor and Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第21题:

    ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor anD.Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第22题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第23题:

    () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

    • A、Project managers
    • B、Project team members
    • C、Sponsors
    • D、Project stakeholders

    正确答案:B

  • 第24题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D