Companycom is planning to do server consolidation on POWER5. The customer has a test environment, a QA environment and a production environment for two applications. Both the test and QA environments are very small and are only utilized when new releases

题目

Companycom is planning to do server consolidation on POWER5. The customer has a test environment, a QA environment and a production environment for two applications. Both the test and QA environments are very small and are only utilized when new releases are being developed and tested. They require less than 1 CPU each. Both production applications require 2 CPUs for day-to-day operation and can require up to an additional 2 CPUs each during abrupt peak requirements. What is the best design for the LPARs?()

  • A、Use micropartitioning for test and QA environments, and DLPAR for the production applications  
  • B、Use micropartitioning for test and QA environment, and CPU pooling for the production applications 
  • C、Create standard LPARs for all test, QA, and production applications to keep all partitions separate and isolated. 
  • D、Create DLPAR partitions for all test, QA, and production applications to keep test from disturbing production environment. 

相似考题
参考答案和解析
正确答案:B
更多“Companycom is plannin”相关问题
  • 第1题:

    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()

    • A、VIO Server
    • B、AIX 5.2 ML4
    • C、Shared Ethernet Adapter
    • D、AIX 5.3 with Advanced Power Virtualization

    正确答案:D

  • 第2题:

    Companycom is planning for a 64-way p5 595. The plan is to use Virtual IO Servers and micropartitioning. What is the maximum number of partitions they can allocate?()

    • A、128
    • B、254
    • C、320
    • D、640

    正确答案:B

  • 第3题:

    Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?()

    • A、Loadleveler
    • B、AIX Workload Manager
    • C、Partition Load Manager
    • D、Tivoli Provisioning Manager

    正确答案:B

  • 第4题:

    关于LTE的主要网元说法正确的为()

    • A、自配置(Self-deployment)
    • B、LTE的接入网E-UTRAN由e-NodeB组成,提供用户面和控制面
    • C、LTE的核心网EPC由MME,S-GW和P-GW组成
    • D、自规划(Self-plannin)

    正确答案:B,C

  • 第5题:

    单选题
    Companycom has a p5 595 with no DVD configured on this server. How can they install the Virtual IO Server code?()
    A

    From the HMC

    B

    From a NFS mount

    C

    From a FTP server

    D

    From any CD or DVD drive on another server


    正确答案: A
    解析: 暂无解析

  • 第6题:

    单选题
    Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
    A

    One single port Ethernet adapter

    B

    Four dual port Ethernet adapters

    C

    Two single port Ethernet adapters

    D

    Eight single port Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第7题:

    After rebooting the machine, Companycom notices that the machine is not performing as well as before. The applications are running slower, and their CPU utilization has increased. How can the customer check to see if a CPU was deallocated?()

    • A、Run the vmstat command
    • B、Run the iostat command
    • C、Run the lparstat command
    • D、Check the logs in the /var/adm/ras directory

    正确答案:C

  • 第8题:

    Companycom has plans to deploy a large database solution. Their primary requirement is minimal user access downtime. They are comparing a single server implementation with a two server deployment. What solution would they use to avoid downtime for OS software maintenance?()

    • A、Apply OS updates once a year
    • B、Utilize a GPFS cluster solution
    • C、Implement a two server deployment with HACMP
    • D、Install a single server implementation with HACMP failover to a second LPAR

    正确答案:C

  • 第9题:

    While planning the logical volume design of a new install, Companycom considered using a striped logical volume for performance. They want to be able to extend the logical volume in the future. Which of the following actions will provide this capability?()

    • A、Add additional logical volumes two at a time
    • B、Add additional physical volumes two at a time
    • C、Create a columned striped logical volume using -C option of mklv
    • D、Create an extendable striped logical volume using -E option of mklv

    正确答案:C

  • 第10题:

    单选题
    Companycom is planning for a 64-way p5 595. The plan is to use Virtual IO Servers and micropartitioning. What is the maximum number of partitions they can allocate?()
    A

    128

    B

    254

    C

    320

    D

    640


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    Companycom purchased a p5 570 with no plans to partition. The customer plans to use the ASMI interface to power on and off the machine. How can ASMI be accessed without a HMC?()
    A

    By typing diags and then going to the ASMI menus

    B

    Through SSH from a TCP/IP connection on the server

    C

    Through WebSM which is connected to a system Ethernet port

    D

    By connecting through a web browser to an HMC Ethernet port


    正确答案: D
    解析: 暂无解析