During a review of environmental requirements before ordering an IBM System z9 server and IBM System Storage DS8700, the customer states that the available power is 220 volts AC.  Which feature should be included with the DS8700 order()  A、Low VoltageB、H

题目

During a review of environmental requirements before ordering an IBM System z9 server and IBM System Storage DS8700, the customer states that the available power is 220 volts AC.  Which feature should be included with the DS8700 order()  

  • A、Low Voltage
  • B、High Voltage
  • C、Remote System z Power Control
  • D、Battery Assembly

相似考题
参考答案和解析
正确答案:A
更多“During a review ”相关问题
  • 第1题:

    111 The review for the specification completeness is performed during which of the following cycles. A. Award cycles

    B. requirements cycle

    C. requisition cycle

    D. solicitation cycle

    E. contractual cycle


    正确答案:C

  • 第2题:

    The most basic reason why dialects should be preserved is that language helps to ______ a culture

    A) retain           B) relate       C) remark                D) review


    答案:A

      参考译文:方言之所以应该被保留的最根本原因是语言有助于留住文化。

      题目分析:本题题干的结构比较复杂,含有两个从句,其中why dialects should be preserved 为定语从句,其先行词为reason,that language helps to retain a culture为宾语从句.注意向本题题干中的这种先行词为reason,由why引导的定语从句翻译的时候需要翻译为...之所以...的原因是...

      考点解析:本题四个选项都是由re开头的,主要是考察形式相近的词语意思的辨析.这道题其实很简单,从题干可以看出dialects和language是同义词,那么需要填入的词一定也是 preserve 的同义词,也就不难选出 retain 了.这是这也是标志词法的一个应用.

     

  • 第3题:

    A customer would like to convert their existing IBM System Storage DS8100 to a DS8700 to gain more capacity. During the TDA review the impact on the running production environment during conversion is discussed. Which of the following must be considered?()

    A. DS8000 model conversions are generally non-disruptive

    B. a model conversion from DS8100 to DS8700 is disruptive

    C. the DS8100 base frame needs to be sent back to the factory for upgrade

    D. during model conversion the logical configuration can be kept, but the system must be rebooted


    参考答案:B

  • 第4题:

    《比较教育评论》(Comparative Education Review)
    美国国际与比较教育学会会刊,1956年创刊,主要刊载国际与比较教育研究领域的研究成果。

  • 第5题:

    以下哪几个选项属于OpenStack社区代码Review的步骤?()

    • A、提交bug或者Blueprint
    • B、创建分支修改代码
    • C、将代码提交给Gerrit
    • D、代码在社区Review

    正确答案:A,B,C,D

  • 第6题:

    What is the main reason for doing a Solutions Assurance Review with the customer? ()

    • A、To revalidate the total solution
    • B、To overcome objections to the solution
    • C、To review the pricing with the customer
    • D、To ensure the customer has the correct applications

    正确答案:A

  • 第7题:

    hans is designing the reviews application. the application will include two forms :review and response, in the view ,the response documents do not appear under the review documents from which they were created, what could be causing this to happen .()

    • A、inheritance in the review form was disabled 
    • B、shared values were enabled on both forms  
    • C、shared field values and field definitions were enabled 
    • D、show response documents in a hierarchy was not enabled

    正确答案:D

  • 第8题:

    A company has acquired another company and is consolidating data centers. During the consolidation, half of the users of a business critical application lost access. The users who maintained access experienced slow performance.  What is the first action the SAN/storage administrator should take to determine the source of the problem()

    • A、review SAN configuration, connectivity, and zoning
    • B、review application parameters for contention or tuning problems
    • C、use internal disk monitoring tools to determine the problem source
    • D、check the disk parameters in the OS setup on the systems

    正确答案:A

  • 第9题:

    You have an Exchange Server 2010 organization.You need to determine why a remote SMTP server rejects e-mail sent from your organization.What should you do?()

    • A、Review the application event logs.
    • B、Review the message tracking logs.
    • C、Set the Protocol logging level to Verbose on the Receive connectors and then review the protocol log files.
    • D、Set the Protocol logging level to Verbose on the Send connectors and then review the protocol log files.

    正确答案:D

  • 第10题:

    单选题
    You have a server that runs Windows Server 2003 Service Pack 2 (SP2) and is configured as a domain controller. You run Windows Update and install a number of device drivers. You restart the server. During the startup process, the server stops. You receive the following stop error message: “0x000000D1 (0x0000000c, 0x00000002, 0x00000000, 0xf27b4e8e) IRQL_NOT_LESS_OR_EQUAL.” You need to identify which device or service is causing the error. What should you do? ()
    A

    Restart the server by using the Safe Mode option. Review the contents of the ntbtlog.txt file.

    B

    Restart the server by using the Last Known Good Configuration option. Review the spupdsvc.log file.

    C

    Restart the server by using the Directory Services Restore Mode option. Review the contents of the ntdtcsetup.log file.

    D

    Restart the server by using the Safe Mode with Networking option. Review the contents of the WindowsUpdate.log file.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    You have a computer that runs Windows 7. You need to identify which applications were installed during thelast week.  What should you do?()
    A

    From Reliability Monitor, review the informational events.

    B

    From System Information, review the Software Environment.

    C

    From Performance Monitor, review the System Diagnostics Report.

    D

    From Performance Monitor, run the System Performance Data Collector Set.


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
    A

    Use eConfig to configure and validate each pSeries and p5 system.

    B

    Engage Advanced Technical Support to review any outstanding technical issues.

    C

    Confirm with the customer that the solution design meets their requirements.

    D

    Perform a Pre-Install Solution Assurance Review to validate required power requirements.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

    A. The project will be completed late.

    B. The critical path has been lengthened.

    C. the costs are being overrun.

    D. Overtime will be required to maintain the original critical path.

    E. None of the above.


    正确答案:E

  • 第14题:

    ( )is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation and review techniques)

    A.allowing looping

    B.allowing for dummy tasks

    C.allowing branching

    D.allowing multiple project end results


    正确答案:B
    图形评审技术(GERT)于1966年首先提出,又称决策网络技术或图示评审技术。是可以对逻辑关系进行条件和概率处理的一种网络分析技术。与CPM相比,允许在网络逻辑和工作延续时间方面存在一定的概率陈述,除了工作延续时间的不确定性外,还允许工作存在概率分支。比如说,某些工作可能完全不被执行,某些工作可能仅执行其一部分,而另一些工作可能被重复执行多次。GERT多使用计算机仿真技术来模拟项目的执行情况。计划评审技术ProjectEvaluationandReviewTechnique(PERT):对单个活动无法进行确定估算时,就其乐观、悲观和最可能的估算进行加权平均的一种估算技术。选项B允许虚拟任务不属于GERT的特点。

  • 第15题:

    The top management of a company will review the organization management review will include consideration of:( a ) customer feedback on quality( b ) processes performance and product conformityThe purpose of management review is ( ).

    A.Control of customers
    B.Control of measurements
    C.Control of qualities
    D.Control of opportunities

    答案:C
    解析:
    解析:翻译:公司的最高管理层将审查组织的管理系统,管理评审将包括以下考虑:(a)客户对质量的反馈(b)处理性能和产品复合型管理评审的目的是( )。A.控制客户B.控制质量C.控制质量D.控制机会

  • 第16题:

    检索式“review in PT”的含义是:()

    • A、检出所有综述文献
    • B、检出所有题目中出现review的文献
    • C、检出所有刊名中出现review的文献
    • D、检出所有主题词字段中出现review的文献

    正确答案:A

  • 第17题:

    ( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).

    • A、Allowing looping
    • B、Allowing for dummy tasks
    • C、Allowing branching
    • D、Allowing multiple project end results

    正确答案:B

  • 第18题:

    A company has acquired another company and is consolidating data centers. During the consolidation, half of the users of a business-critical application lost access. The users who maintained access experienced slow performance.  What is the first action the SAN/storage administrator should take to determine the source of the problem()

    • A、review SAN configuration, connectivity, and zoning
    • B、review application parameters for contention or tuning problems
    • C、use internal disk monitoring tools to determine the problem source
    • D、check the disk parameters in the OS setup on the systems

    正确答案:A

  • 第19题:

    Which tasks are necessary to perform a data migration using DFSMS?()

    • A、Microcode review and data classification
    • B、Initialization and data classification
    • C、Microcode review, ACS routine, and back up of data
    • D、Data classification, ACS routine, and back up of data

    正确答案:D

  • 第20题:

    Your network consists of a single Active Directory domain.? All domain controllers run Windows Server 2008. You need to identify the Lightweight Directory Access Protocol (LDAP) clients that are using the largest amount of available CPU resources on a domain controller. What should you do()

    • A、Review performance data in Resource Monitor.
    • B、Review the Hardware Events log in the Event Viewer.
    • C、Run the LAN Diagnostics Data Collector Set. Review the LAN Diagnostics report.
    • D、Run the Active Directory Diagnostics Data Collector Set. Review the Active DirectoryDiagnostics

    正确答案:D

  • 第21题:

    单选题
    A customer would like to convert their existing IBM System Storage DS8100 to a DS8700 to gain more capacity. During the TDA review the impact on the running production environment during conversion is discussed. Which of the following must be considered?()
    A

    DS8000 model conversions are generally non-disruptive

    B

    a model conversion from DS8100 to DS8700 is disruptive

    C

    the DS8100 base frame needs to be sent back to the factory for upgrade

    D

    during model conversion the logical configuration can be kept, but the system must be rebooted


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    检索式“review in PT”的含义是:()
    A

    检出所有综述文献

    B

    检出所有题目中出现review的文献

    C

    检出所有刊名中出现review的文献

    D

    检出所有主题词字段中出现review的文献


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    What is the main reason for doing a Solutions Assurance Review with the customer? ()
    A

    To revalidate the total solution

    B

    To overcome objections to the solution

    C

    To review the pricing with the customer

    D

    To ensure the customer has the correct applications


    正确答案: A